VCAT Volume 12 No 6
1. Another dwelling refused in Silverleaves because of potential flooding impacts
It may be recalled that in Doyle v Bass Coast SC [2024] VCAT 895 the Tribunal set aside the Council’s decision to approve a single dwelling in Silverleaves, part of the Cowes township at Phillip Island because of concerns with inundation from projected sea level rise (see editorial comment VCAT Vol 12 No 1). Melbourne Water, as determining referral authority, objected to that application.
In Fellows v Bass Coast SC [2025] VCAT 43, which concerned another single dwelling in Silverleaves, the Tribunal considered the Applicant’s appeal against the Council’s decision to refuse the application. Council officers supported the application and Melbourne Water, contrary to Doyle, did not object to the application subject to conditions on any permit issued.
The Tribunal supported the Council’s refusal. In so doing, it considered that:
- The Land Subject to Inundation Overlay (LSIO) has been applied to identify an area of Victoria that is at risk of present day and future coastal inundation east of Coghlans Road. Under present day conditions a small proportion of this land area is subject to inundation, but relevantly, a high proportion of that land area will be subject to inundation under 2100 projected sea level rise and storm surge levels due to the effect of climate change. Other land not so inundated will be isolated for varying time periods from safe access to higher ground due to this inundation.
- Local planning strategies for housing and the management of coastal inundation hazards discourage future development east of Coghlans Road. The Tribunal could not identify any planning policy imperative or support for development that would overcome its findings and conclusions about the risks arising from the inundation hazard.
- There are at this time, no adaptation responses for Silverleaves which would indicate future protection of this settlement from sea level rise and storm surges or provide support to residents by way of warning systems for early evacuation. The present projections for future inundation and the associated risks therefore are to be given significant weight in assessing this proposal.
- The design of the development overcomes present day minor tidal storm surge incursions and can accommodate future forecasted tidal storm surge incursions without a risk to the property. However, the location of the development would expose future residents to the hazard of isolation during inundation events and the hazards arising from inundated access if they do not leave the subject land before the inundation cycles begin.
- There is a high degree of probability that future residents of this proposed development who seek to move through the areas of inundation may be exposed to hazardous conditions. This is an outcome that policy and the purposes of the LSIO seek to avoid.
Further, the Tribunal considered that to wade to refuge under the 2060 inundations scenario presents a scenario for a 1.2km walk through sections of flooded road and that by 2100, it’s a wade along a 1.5km road network that is inundated to varying degrees and unsafe even for an adult at varying times. The Tribunal stated:
It is an unfair burden to place on future land owners or occupants to distinguish between these safe and unsafe conditions and make a reasoned decision about when it is safe to evacuate from the residence.
While experts may know and can advise of safe times to evacuate, the reality is that lay people cannot and at present there is no warning or advice systems in place for Silverleaves to assist in a safe and orderly movement under the projected inundation conditions. [110-111]
One of the Applicant’s submissions was that future adaptation measures addressing coastal inundation could reduce or eliminate the risk, noting that the risk is a future risk. However, there were no specific adaptation measures the Applicant could point to.
It is interesting to note that in a recent decision of the Victorian Building Appeals Board, Syme v Port Phillip City Council [2024] VBAB 142, the Board set aside the decision of the Council to refuse the construction of a dwelling on land liable to flooding pursuant to r 153 of the Building Regulations. Amongst other reasons, the Board held:
- Melbourne Water’s notional year 2100 flood levels are not a realistic estimate or one likely to occur;
- the life of the dwelling will expire well before the predicted flood level rise;
- there is not likely to be a danger to the life, health or safety of the building’s occupants due to flooding of the subject land after completion of the proposed dwelling. Various considerations include:
- the floor level of the proposed dwelling at 2.3m AHD is an improvement from the existing dwelling on the subject land;
- the floor level of the proposed dwelling at 2.3m AHD and the first floor at 5.25 AHD are above the current flood level and the 2100 1% AEP projected storm tide inundation level; and
- flooding were it to occur at the subject land would be of short duration, without wave action, and for the possible flood level in 2100, of low hazard to adults and children; the creation of the additional storey at a level well above the specified flood level creates a refuge that would allow the occupants of the building to shelter from any such flood.
See also:
- Guide to Planning Appeals: Flood risk
2. Keep Dancing
Practitioners may recall that in Dance v Colac Otway SC [2024] VCAT 443 the Tribunal issued an Interim Order that supported a proposed tourist accommodation (group accommodation and caretakers dwelling) pursuant to permissions under the Rural Conservation Zone (RCZ) and the Significant Landscape Overlay (SLO). The Interim Order required changes to be made to the plans.
Because the required changes to the plans could potentially impact on matters under the Erosion Management Overlay (EMO) and the Bushfire Management Overlay (BMO), matters which were not within the Tribunal’s jurisdiction having regard to Myers v Southern Grampians Shire Council [2023] VSC 658, the Interim Order required the Responsible Authority to advise the Tribunal and the other parties of the decision (including the permit conditions if a permit is to issue) it had made relating to the amended permit application (to be lodged by the Respondent permit applicant) pursuant to the EMO and the BMO.
However, the Interim Order was not able to be acted upon as envisaged because there were further changes to the plans.
In Dance v Colac Otway SC (No. 3) [2025] VCAT 52, the Respondent permit applicant advised the Tribunal at a Practice Day hearing it has since gained conditional support from the CFA under the BMO and support from Council for planning permission to be granted under both the EMO and the BMO. The support from both authorities required further amended documents and amendments to the proposal, being amendments made to the VCAT substituted amended plans and documents.
There were differences of views at the Practice Day hearing as to the way forward from here.
The Objector applicants for review suggested the Tribunal consider remitting the proceeding back to Council with directions under section 51(2)(d) of the Victorian Civil and Administrative Tribunal Act 1998 (VCAT Act), noting that Council may then decide to take the application as now amended back to a public notice process.
The Respondent suggested an alternative process whereby they could work with Council to come up with three documents:
- A BMO and EMO permit for the Tribunal’s information (i.e. take the draft permit that Council has provided to all parties and the Tribunal, and make changes to it based on the issues raised in the Tribunal’s order for this Practice Day hearing and other issues that have arisen during this hearing).
- A document outlining the order the Tribunal could make granting planning permission under the RCZ and SLO. This could have two versions so one version identifies any conditions remaining in dispute.
- A document showing what the final permit could look like if Council combines the planning permissions and the conditions associated with each of those planning permissions into one planning permit.
However, the applicants for review submitted the above process is unorthodox and potentially compromising, particularly given the Tribunal’s limited jurisdiction. They were concerned this type of process may set a precedent in the circumstance where it is not the Tribunal’s responsibility to fix things up and bring together all of the planning permissions. They considered the fair way to deal with this matter is to send it back to Council.
Whilst the Respondent argued the changes were minor, which appeared to underpin their suggestions on the way forward, the Applicants expressed a concern about the acceptability of the merits of the changes, particularly in regard to the SLO.
The Tribunal decided to the best way forward was to invite the Council to reconsider its decision. It noted the following issues:
- It is unclear how the parties and the Tribunal are supposed to distinguish between which conditions relate to which permissions;
- Having a permit that will contain two sets of conditions (e.g. for the BMO/EMO on a further amended proposal and for the RCZ/SLO on a VCAT substituted amended proposal) will require endorsement of two sets of plans that contain differences; and
- Council will be put in the circumstance suggested by the Respondent permit applicant that it will undertake a section 72 amendment to bring the VCAT substituted amended proposal into line with the BMO/EMO differences. It may be that Council may not wish to approve a section 72 amendment and may want the Tribunal to be involved through a section 87A application. This would create yet another process for this permit application.
Accordingly, the Tribunal considered that there may be need for another practice day hearing or a hearing of the merits relating to the Applicant’s concerns, including their issue about the absence of a landscape plan and photomontages.
The Tribunal observed that it would then be in a position to make a final decision in this proceeding, and will have the benefit of Council’s view on the whole of the permit application. In that case, its reasons could refer to Council’s new decision and it could attach Council’s new decision in full as an appendix to its decision (as opposed to attaching conditions imposed by the Tribunal in an appendix, as is the normal course). This review proceeding would be effectively a review of Council’s new decision, as explained in section 51A of the VCAT Act. This puts the Tribunal into the position of needing to just consider the merits and submissions about the changes that have been made since its interim decision and the conditions in Council’s new decision relevant to the SLO and RCZ.
As we stated in the editorial comment at VCAT Vol 11 No 11, practitioners in planning and legal circles have raised concerns about the potential implications of the Myers decision which results in segregated decision-making. Seeking to resolve matters through VCAT rather than Council also prolongs the decision-making process (noting that the further hearing day is not scheduled until 14 May 2025, some four months after the further practice day hearing). Reform in this area is urgently required, particularly if the goals of a simplified and integrated planning system are still the overriding legislative objectives. The review of the Planning and Environment Act 1987 provides the opportunity for potential reform to be pursued.
See also:
- Guide to Planning Appeals: National Trust principle > Relevance of specific clauses and decision guidelines in the planning scheme with control trigger
3. Unenforceable restrictive covenant removed
In Re 313 Investments & Holdings Pty Ltd [2025] VSC 9, the Supreme Court has upheld an owner’s application for declaration that a restrictive covenant that limited the types of uses in a business park was unenforceable due to there being no land that enjoys the benefit of the subject covenant.
The covenant was registered on the titles of the subject land in 2017, when the subject land was part of a single lot (‘parent land’). It was registered when the title to the parent land was transferred to the registered proprietor preceding the current owner by a previous owner, who was the developer of the business park.
The title of the ancestor lot was cancelled on 24 November 2010, more than six years prior to the registration of the subject covenant. As a consequence of sequential subdivisions of the land within the ancestor lot, there are now 222 lots in the area within the ancestor lot, including the two lots that make up the subject land.
The owner proposes to develop the subject land as a place of worship, which is one of the uses prohibited by the subject covenant.
In agreeing with the Owner’s submissions, the Court stated that:
Since the title of the ancestor lot was cancelled, the lots within the ancestor lot within which the subject land is located have undergone eight separate subdivisions. Therefore, while it is tolerably clear from the language of the subject covenant and the location of the subject land within the business park that the drafter of the subject covenant intended to benefit the land originally within the ancestor lot other than the parent land, that land no longer existed at the time the subject covenant was registered. It is for that reason that the owner says that the subject covenant is unenforceable, because there is no land that enjoys the benefit of the subject covenant, and the subject covenant should be discharged. For the same reason, the owner says that the Court is neither required to nor should it, exercise its power under s 84(3) of the Property Law Act 1958 (Vic) (‘PLA’) to direct the owner to notify the registered proprietors of any or all of the properties within the business park of the owner’s application to discharge the subject covenant. [9]
See also:
- Guide to Planning Appeals: Restrictive covenant > Supreme Court cases
4. More on National Trust principle and relevant considerations
The Tribunal continues to deal with complex issues on the National Trust principle and relevant considerations.
In Carolbridge Pty Ltd v Yarra CC [2025] VCAT 83, which involved an application for an 11-storey mixed-use office building, at the commencement of the Hearing the parties requested the Tribunal determine questions of law prior to consideration of the merits.
Council had supported the application and a third party challenged the Council’s decision.
The subject site is in the Commercial 2 Zone and affected by two Design and Development Overlays, schedules 1 and 5, and Significance Landscape Overlay, schedule 1. Other permissions included Development Contributions Overlay schedule 1 and to reduce car parking requirements under Clause 52.06.
The questions of law essentially involved matters concerning relevant considerations under the two DDOs and the SLO.
In considering the questions of law, the Tribunal referred to key cases including National Trust of Australia (Vic) v Australian Temperance & General Mutual Life Assurance Society Ltd (1976) VR 592, Boroondara City Council v 1045 Burke Road Pty Ltd [2015] VSCA 27 and Viva Energy Australia Pty Ltd v City of Greater Geelong [2023] VSC 586.
Myers v Southern Grampians Shire Council [2023] VSC 658 was also considered, particularly in the context of Council approving the application under the DDOs and SLOs and where there are no third parry appeal rights.
The Tribunal’s analysis considers the question of relevance against the above authorities. In broad terms, the Tribunal considered the third party applicant was seeking to adopt a wider approach as to relevant considerations (and therefore the Tribunal’s scope of consideration) than what the above authorities were indicating. However, it noted that:
- the authorities are yet to consider the relevance of considerations in the exercise of a discretion for building and works permission under a DDO as the main cases to date have considered relevance of considerations in relation to buildings and works permission under a building height control, to subdivision permission under a DDO, to buildings and works permission under an inundation overlay and to demolition permission under a heritage overlay; and
- there are no inconsistencies as claimed by the Applicants in the reasoning between 1045 Burke Road and other authorities such as Viva Energy in relation to what are relevant considerations.
The effect of the Tribunal’s determination was that matters pertaining to wind impacts; specific views to heritage sites; the acceptability of mass and bulk of the proposed building; shadow impacts; levels of activation of the ground plane; whether the proposal is a piecemeal application; and owners corporation consent were not relevant considerations.
The impact of the development on the pedestrian experience was a relevant consideration because the construction of bollards and footpaths in the DDO2 area affects the ‘pedestrian experience’ within that area.
The Tribunal’s analysis required a painstaking exercise of considering each purpose and decision guidelines of the DDOs and SLO. The Applicants warned that a ruling that the matters in question were not relevant runs counter to the off-cited passage of the Supreme Court in Pacific Seven Pty Ltd v City of Sandringham [1982] VR 157, that stresses the need to avoid ‘exotic legalism’ that frustrates the ends of justice.
The Tribunal stated it was conscious of this passage, but the parties have agreed to raise questions of law about these matters and so the Tribunal must decide relevance about contested matters before the Hearing. If the answers to the questions of relevance abbreviate what is relied on at the Hearing and shortens the duration of the Hearing, it will reduce the parties’ costs and the call on the Tribunal’s resources.
Further, the Tribunal considered that application of the National Trust principle should not be characterised as ‘exotic legalism’ but as no more than application of the law.
Be that as it may, your editors consider that the somewhat haphazard approach of some of the changes to Victoria’s planning system over recent years, particularly in relation to exemptions from notice, which has resulted in some parts of applications being exempt but other parts are not, challenge the legislative objectives of integrated decision making with appropriate public participation in decision making, as per section 4(2)(h) of the Planning and Environment Act 1987.
See also:
- Guide to Planning Appeals: National Trust principle > Relevance of specific provisions and decision guidelines in the planning scheme with control trigger
5. Restricted recreation facility refused in industrial zone
We have commented on some cases concerning restricted indoor recreation facilities in industrial zones in recent times, see for example Thuliwal Transport Pty Ltd v Wyndham CC [2023] VCAT 1135 and Sansai Electronics Pty Ltd v Greater Dandenong CC [2023] VCAT 1130, editorial comment VCAT Vol 11 No 4.
In Auslander Developments Pty Ltd v Greater Dandenong CC [2025] VCAT 111, the Council had refused a permit for a restricted recreation facility (badminton and basketball) largely because of concerns that the use is not consistent with the purpose of the Industrial 1 Zone and its incompatibility with other land uses.
The site is proximate to land located within the Industrial 2 Zone which Council submitted is within the state significant industrial precinct of Dandenong South. Clause 17.03-3S seeks to ‘protect significant industrial land’.
In supporting Council’s refusal, the Tribunal considered that:
- the establishment of the use will make the land no longer available for industrial and associated commercial uses, which is of even greater concern given the relatively large size of the premises;
- while there is recognition that there are some non-industrial uses in this locality, they are on significantly smaller premises that makes little difference to the overall supply of industrial land;
- it is not appropriate to establish a new sensitive use within the industrial zone on the basis of other existing sensitive uses – whilst these sensitive uses may cease to exist, it does not justify adding to the number of sensitive uses that may impact on the functional operation of the industrial area; and
- there is a sweep of planning zones that potentially can accommodate the proposed restricted recreation facility without encroaching on industrial land that the planning policy seeks to protect from commercial, residential and other sensitive uses.
Despite the Tribunal’s comment about the availability of more preferred zones to locate the facility, it did not find that this was a significant failing of the proposal.
See also:
- Guide to Planning Appeals: Restricted recreational facility, Indoor recreation facility
6. Whether rural workers accommodation ancillary
Amendment VC202 to the Victorian Planning Provisions (VPPs) introduced a definition for ‘rural worker accommodation’ at Clause 73.03 of the scheme as well as:
- introduced a permit exemption for use of land for rural worker accommodation that accommodates no more than 10 persons in the Farming Zone (FZ); and
- introduced a permit requirement for use of land for rural worker accommodation that accommodates no more than 10 persons in the FZ.
In Redland Fruit Pty Ltd v Swan Hill RCC [2025] VCAT 127, the Tribunal considered an application for declaration pursuant to section 149B of the Planning and Environment Act 1987 (P&E Act) that a Certificate of Compliance be granted confirming that the proposed use and construction of accommodation on the orchard for workers is ancillary to the purpose for which the orchard is being used.
The proposed accommodation includes 14 four-bedroom units, with two beds in each bedroom (accommodating up to 112 persons), two two-bedroom units, with two beds in each bedroom (accommodating up to eight persons), three dining units, three kitchens and three amenity blocks, a driveway (labelled ‘road access’), 23 car spaces and an area for bus parking.
The accommodation is confined to that part of the southern lot that is on the east side of Long Lake Road. It has an area of 1.773ha, however the Applicant submitted that the subject land will be consolidated into one lot of 99.67ha as part of the proposal.
This was the second application for declaration made by the Applicant. In Redland Fruit Pty Ltd v Swan Hill Rural CC [2023] VCAT 601, the Tribunal granted a declaration that proposed worker accommodation was ancillary to use of or horticulture subject to a number of parameters, including:
- a maximum of 32 workers may be accommodated on the land;
- the workers may only be accommodated during the harvest season that is, from July through to December;
- the workers accommodation may only be used by workers actively working on the land for the harvesting of the fruit from the land; and
- the accommodation must be provided at no cost to the workers and their rooms must not be serviced.
Council was opposed to the declaration on the basis that a certificate must be refused because the whole of the use or development would require a permit or is prohibited under the planning scheme.
The Tribunal refused to grant the application for declaration. Having regard to the type of relevant factors identified in Mildura RCC v Lando [2020] VCAT 793, the Tribunal found:
- Scale or intensity – accommodation for up to 128 workers is significantly greater than the 32 workers maximum in the declaration granted for part of the subject land in the earlier application;
- Duration and frequency – the proposal is for accommodation during the whole year, partly because Redland submits the harvest period for different fruit could be at all times of the year having regard to a range of circumstances, including varying seasonal conditions and fruit condition; and
- Type of workers – it appeared to be inferred in the earlier application that the declaration did not extend to workers involved in processing the fruit – ie in packing or cool room activities.
Because the proposal is not an ancillary use or activity that complies with the requirements of the planning scheme, the Tribunal stated that it is strictly unnecessary to determine whether the proposal is a development that complies with the planning scheme. However, the P&E Act allows a certificate to be issued stating that a use complies with the requirements of a planning scheme even if development for the use does not comply with those requirements.
With respect to development, the Tribunal found that the condition in the FZ that workers accommodation is not more than 10 persons accommodated away from their normal place of residence was not met because 120 (or 128) persons may be accommodated in the relevant way.
Accordingly, permission is required to develop the land for the proposal and a certificate cannot be issued because the development, in the absence of permission, does not comply with the planning scheme.
See also:
- Guide to Planning Appeals: Rural workers accommodation
7. Whether exemption from public open space contribution for two lot subdivision
In Merri Creek Views Pty Ltd v Merri-bek CC [2025] VCAT 146, the Applicant appealed against a condition of permit for a two lot subdivision requiring a 5.7% public open space contribution.
Clause 53.01-1 of the planning scheme includes a range of exemptions from the public open space requirements. In this matter there is one exemption that is in contention:
A subdivision is exempt from a public open space requirement specified in this scheme if:
…
It subdivides land into two lots and the council considers it unlikely that each lot will be further subdivided.
The Tribunal referred to some recent cases where the question of ‘likelihood’ as to whether each lot will be further subdivided, including Perera v Casey CC [2021] VCAT 1178. In that case, the Tribunal also considered numerous cases that dealt with this particular exemption. The Tribunal provided a list identifying some of the key principles in these cases:
- What is important is the objective opinion of the responsible authority, and the Tribunal on review, and not the subjective intentions of the landowner;
- Whether further subdivision is or is not unlikely is to be assessed objectively based on the physical facts and circumstances of the subject land (including site constraints) and its surrounds and the planning context of same, including any planning controls and policies that guide future development;
- In a temporal sense, there is no warrant to confine what is meant by ‘future’ to a defined period of months or years. However, the greatest weight must be given to the present site context, controls and policies; and
- Whether something is “unlikely” is not the same as whether something is impossible – some cases have referred to it meaning ‘improbable’.
Further, consistent with the approach in Farha v Darebin CC [2023] VCAT 448, based on the statutory construction of the exemption, the Tribunal also considered both created lots must be unlikely to be further subdivided (‘each lot’) to have the benefit of the exemption.
In concluding that the condition be retained in the current proceeding, the Tribunal stated:
I accept that there are challenges in further subdividing the site based on the zone and policy controls, slope, size of site and the other constraints mentioned driven by cl 55 in particular. However, while this is an area of ‘minimal change’ in policy, it is not an area of no change……
In summary, despite these challenges, there is nothing before me that suggests subdivision and further development is impossible. I then need to address the question of whether further subdivision is likely, or conversely unlikely or improbable. [17-18] (Tribunal emphasis)
See also:
- Guide to Planning Appeals: Public Open space contributions > Exemptions where lots cannot be further subdivided