1. Remitting applications for reconsideration to the RA

Section 51(2)(d) of the Victorian Civil and Administrative Act 1998 states:

In determining a proceeding for review of a decision the Tribunal may, by order—

set aside the decision under review and remit the matter for re-consideration by the decision-maker in accordance with any directions or recommendations of the Tribunal.

There have been two recent cases where the Tribunal have remitted applications to the Council.

In the first case, Smith v Yarra Ranges SC [2024] VCAT 1036, Council issued a Notice of Decision for buildings and works associated with the placement of a tram car and pergola (for the purpose of a retail premises) and a reduction in car parking requirements.

Placing the tram car required the use of a crane and the neighbour’s property. This apparent arrangement was a factor in Council supporting the application. However, by the time of the VCAT appeal the Permit Applicant advised the Tribunal that the neighbour no longer consented to the use of his land to lift the tram car and that an amending application and accompanying amending plans were now being prepared.

This resulted in various questions at the practice day hearing from parties and the Tribunal. Those matters included whether additional permissions would be triggered by modifications to be advanced, the extent of any further notice beyond parties and in accordance with PNPE9, and whether the matter should be remitted to the Council.

Both the Council and Applicant, being the neighbour, supported remitting the matter, however the Respondent was strongly opposed.

In deciding to remit the matter, the Tribunal noted that:

  • there are various uncertainties about the proposal that is the basis of the permit application, as evident in submissions for the Respondent;
  • the Respondent no longer intends to seek to amend plans, however, modifications to the proposal that was the subject of the Notice will be needed to address the non-use of the neighbouring land and, it appears, potentially with respect to fencing which remains a factual point in dispute. There are potentially additional and new considerations, such as may apply to any potential vegetation impacts; and
  • the permit application was processed by the Council on the basis of material provided by the permit applicant that was factually incorrect insofar as the intent to use of 373-375 Mt Dandenong Tourist Road had not been agreed and will not be agreed to by the owner of 373-375 Mt Dandenong Tourist Road.

The Tribunal noted remitting matters is not often exercised. It stated:

A decision to remit a matter to the responsible authority is not made lightly or without careful consideration of all the facts and circumstances. I have determined that remittal is appropriate in the particular circumstances of this proceeding including the following combination of matters: 

    • It is necessary for inaccuracies to be rectified and/or modifications to be fully and accurately documented in the permit application for clarity, certainty, and to enable a full assessment under the relevant provisions of the Yarra Ranges Planning Scheme.
    • It remains uncertain as to what revisions are sought or needed and therefore whether there would be any additional permit trigger/s; and whether those persons originally notified of the permit application should be given the opportunity to consider any amended permit application and/or whether additional persons or authorities would need to be given notice.
    • The application for review is by an objector in response to a specific permit application. Errors and uncertainties with respect to the permit application are for the permit applicant to rectify or address.
    • The matter is not ready for a compulsory conference or hearing. [20]

In the second case, Sharp v Mornington Peninsula SC [2024] VCAT 1056, application had been made for a proposed change of use (from Poultry farm) to Vehicle storage yard with Caretakers dwelling.

Council issued a Notice of Decision and an objector lodged an appeal. The matter failed to resolve at a Compulsory Conference.

The Respondents circulated amended plans and foreshadowed these would be relied upon at the forthcoming merits hearing through a request to substitute them for the earlier permit application plans.

In seeking to substitute the plans, the Respondents advised in correspondence that the changes are minor, are proposed largely by way of clarification, and clearly reduce the scope of the application and its potential impacts.

The Applicants raised various procedural fairness concerns:

  • There has been a considerable elapse of time since notice of the permit application occurred such that the identity of persons previously notified of the permit application may have changed;
  • No subsequent notice of the additional material given to Council after completion of public notice occurred and Council’s planning register indicates that no application was made by the Permit Applicant to amend the permit application before the Council determined it;
  • The proposed amendments include different features from the material which was the subject of public notice. New or additional consequential impacts affecting persons to whom public notice was originally given may now arise; and
  • On the basis of the NOD’s drafting and content of the officer’s report assessing the permit application, there is some doubt and confusion as to what plans actually informed Council’s decision to grant a permit.

In declining to adjourn the hearing so as to allow notice to be properly given to all persons and within the timeframes specified in VCAT Practice Note PNPE9, the Tribunal stated:

This proceeding under s 82 of the Act also brings into sharper focus the Tribunal’s role in the exercise of its review jurisdiction. It is not an appropriate use of the Tribunal’s limited resources to be performing the role of the responsible authority as the original decision maker in the first instance.

At its core, the proposed amended plans seek to overcome various procedural and administrative deficiencies that occurred during council’s processing of the permit application.

The usual procedures for amending plans under VCAT Practice Note PNPE9 should not be relied upon to cure deficiencies with this permit application.

The Tribunal concurs with the applicants’ submissions that what has unfolded is a ‘real mess’, and it is clear to the Tribunal that the permit application is not decision ready in this proceeding.

I find that the exercise of the Tribunal’s powers under s 51(2)(d) of the VCAT Act is the preferred course of action. This will allow proper notice of the amended proposal to be given and for the council to reconsider its decision. [47-51]

Both cases demonstrate that unresolved matters during the application process should be for permit applicants and responsible authorities to sort out, not the Tribunal, particularly if it involves changes to applications and potentially affect third party rights.

See also:

  • Guide to Planning Appeals: Appeals > Remitting a matter back to the original decision maker

2. No permit required if the benefit of the permit no longer applies

Practitioners would be well aware of the Supreme Court case Benedetti v Moonee Valley City Council [2005] VSC 434 that laid down two criteria for the ongoing enforceability of development permit conditions:

  • first, the condition must, by its terms, be one which operates on an ongoing basis beyond completion of the development authorised by the permit; and
  • second, the land in question must continue to take the benefit of the permit.

In Mitchell v Hobsons Bay CC [2024] VCAT 1060, application was made to amend endorsed plans to allow demolition of a gate and brick fence. The land is in the Public Park and Recreation Zone (PPRZ) and is also within a Special Building Overlay (SBO). The proposed demolition was consistent with the Master Plan prepared by the Council.

A third party objector was opposed to the demolition of the fence and gates. Part of the objection was made because there had been a previous agreed outcome between the then applicant for the permit, the RSL, and the objector.

Despite the objection, both the Responsible Authority and Respondent (Hobsons Bay City Council) contended that the Tribunal does not have jurisdiction to consider matters related to the RSL permit (including any amenity impacts arising from the existing or future operation of the RSL) or the adoption and implementation of the Master Plan for the following reasons:

  • The application does not propose any amendments to the RSL permit. Any amendments sought or required to the RSL permit are matters for another day. They are not before the Tribunal.
  • The design and implementation of a Master Plan for the reserve is not a matter that requires planning permission and is not a matter that the applicant, or other residents, can seek to review.

Further, it was submitted that the current proceeding is ‘more novel’ than Benedetti, because the question of whether a permit is required in this instance is dependent on the identity of the permit applicant.

The Tribunal also observed this proceeding differs from Benedetti in another two ways:

  • the wording of the ‘secondary consent’ condition in the gate permit differs from that considered in Benedetti; and
  • in Benedetti, part of the building authorised by the permit was to be retained.

The Responsible Authority explained that provided the Respondent as landowner and public land manager undertakes the demolition a permit is not required because under Clause 62.02-1 of the Planning Scheme the Respondent does not require planning permission to construct or carry out buildings and works with an estimated cost of $1,000,000 or less carried out by or on behalf of a municipality. However, the same cannot be said of the RSL, which leases part of Reserve from the Council.

On the other hand, the Appellant contended that Condition 2 cannot impose a greater degree of land use regulation than the planning scheme control itself. This contention was not accepted by the Tribunal for a number of reasons.

The Tribunal held that if the gate and brick wall authorised by the gate permit are physically removed or demolished in their entirety, no one (be it the landowner or any occupier) will derive a benefit from the gate permit. It noted that in Benedetti it was stated [at 30]:

In my view Condition 1 continues to have effect while the owner of the land takes the benefit of the permit. It will have no effect if the permitted development which includes an element over six metres is demolished, but while such development is maintained, the conditional obligation not to modify the layout or the size of the buildings persists. (Tribunal emphasis)

Hence, the Tribunal stated:

Following the Court’s line of reasoning, I find that if the gate and brick wall authorised by the gate permit are physically removed or demolished in their entirety, no one (be it the landowner or any occupier) will derive a benefit from the gate permit. The permit will no longer have a role to play in regulating development on the land – and cannot be said to burden the land with any ongoing obligation. [54]

This case essentially confirms an aspect of the Benedetti case that the benefit of a permit is limited to elements of the permit that are subject to a planning approval. This includes consideration of permit exemptions that may apply elsewhere in the planning scheme, in this case the permit exemptions that apply to municipalities and other public authorities. It is important for practitioners to be aware that the benefit of a permit are not open-ended.

The Tribunal summarily dismissed the application under section 75 of the Victorian Civil and Administrative Act 1998.

See also:

  • Guide to Planning Appeals: Permit > Amendment to permit > Whether permit spent, Jurisdiction of the Tribunal

3. Questions on whether Cultural Heritage Management Plans required

Two recent cases have considered whether a Cultural Heritage Management Plan (CHMP) is required.

In the first case, Westernport Marina Pty Ltd v Mornington Peninsula SC (Red Dot) [2024] VCAT 1041, the Tribunal at a practice day hearing considered whether a CHMP was required on the basis of whether excavated, filled/reclaimed land and breakwater land associated with the Westernport Marina constituted significant ground disturbance pursuant to the Aboriginal Heritage Regulations 2006 (AH Regulations).

The buildings and works included the construction of vertical boat stacking sheds, a hardstand area, boat ramp and forklift launching area and the installation of service rows.

Both the Council and the Applicant contended that a CHMP was not required for the proposal, although they differed somewhat as to why. In essence, both the Council and the Applicant contended that because the land comprises both excavated areas and reclaimed land, it either does not trigger both limbs of regulation 7 of the AH Regulations, or, the proposed activity is an exempt activity.

The Tribunal agreed with the parties that the land, being the activity area for the purposes of the Aboriginal Heritage Act 2006 and AH Regulations, comprises:

  • some areas that have been excavated from the previous layout of the land and the shoreline; and
  • some areas that have been filled to create land where previously there was just seabed.

As to whether the land is in an Area of Cultural Heritage Sensitivity (ACHS), the Tribunal found that:

  • the part of the land that is the marina basin is not an ACHS, nor are the buildings and works in that area a High Impact Activity (HIA);
  • the part of the land that is the breakwater is not an ACHS, nor are the buildings and works in that area a HIA; and
  • whilst the part of the land that is created, filled or reclaimed and is to contain the vertical boat stacking shelves and the hardstand area might be an ACHS (underneath the fill), the proposed buildings and works in that area will not constitute a HIA.

As such, in relation to the activity the subject of this proceeding, regulation 7 of the AH Regulations is not triggered because whilst part of the activity area might be an ACHS, all or part of the activity is not a HIA and that a mandatory CHMP is not required for the purposes of section 52 of the AH Act.

Further, the Tribunal found that, even if it was wrong on the above findings, it considered regulation 46(3) applies to the application. This regulation states that the construction of a building or the construction or carrying out of works on land is not a HIA if it is for, or associated with, a purpose listed under subregulation (1)(b) for which the land was being lawfully used immediately before 28 May 2007.

The Tribunal found that having regard to the material before it, which included the 1982 Permit and its plans and the various photographs:

  • it is clear that the proposed buildings and works are for or associated with the use of the land for the Westernport Marina, being use for the purpose of a recreational boat facility (marina); and
  • it is more likely than not that the land was being lawfully used for the Westernport Marina immediately before 28 May 2007.

In the second case, Ashlyn Springs Pty Ltd v Yarra Ranges SC [2024] VCAT 1057, the Tribunal considered whether an updated CHMP was required for a five lot residential subdivision. A previous application for a 48 lot subdivision had been refused.

Council argued that the approved CHMP was not sufficient for this proposal/activity because the activity in the approved CHMP is ‘an intense subdivision’ in the northeast corner of the site and ‘nothing elsewhere’. In comparison, the current proposal/activity is a five lot subdivision of the entire site, so the CHMP should have been updated.

On the other hand, the Applicant submitted that the HIA in the approved CHMP and the proposed activity in the planning application are the same, being a residential subdivision.

Both Council and the Applicant relied on Lake Park Holdings Pty Ltd v East Gippsland SC (Red Dot) [2014] VCAT 826. The Applicant describes this as ‘the leading authority on the correct approach to the question’:

… as to whether, on a fair and objective reading of the pre-existing CHMP as a whole, the CHMP still reasonably covers or contemplates the activity now proposed in the amended development proposal that requires the new permit. ..

In holding that a new or updated CHMP was not required, the Tribunal stated:

The …  Applicant’s plan illustrates that the proposed activity continues to be a residential subdivision of the whole of the activity area. The subdivision includes a road and proposed building envelopes. They are all within the area previously approved to contain the residential lots and associated infrastructure.

The above extract also illustrates that the balance of the five proposed lots all contain a portion of the remaining activity area. The plan of subdivision shows no details of any further development within the balance of each lot. As such, the proposed plan of subdivision proposes a consistent high impact activity (i.e. a residential subdivision) but with a lesser extent of proposed development, including a far less extent of works in the south and west sections of the activity area.

As such, I find the high impact activity of the approved CHMP and this proposal are similar and the approved CHMP can be relied upon in this respect. [28-30]

See also:

  • Guide to Planning Appeals: Cultural Heritage Management Plan > Exemption from requiring a CHMP

4. Are ‘token’ applications for compensation under a PAO legitimate?

It may be recalled that in Kilpatrick v Wyndham CC [2022] VCAT 474 (editorial comment VCAT Vol 9 No 9), the Responsible Authority, acting on the advice of Head, Transport for Victoria (TfV), a determining referral authority, imposed a  condition requiring that four dwellings on four separate lots be relocated outside the part of the land affected by a Public Acquisition Overlay (PAO) to avoid the payment of compensation under section 99(a)(ii)(B) of the Planning and Environment Act 1987. The Tribunal disallowed the appeal on the basis that the subject land is or may be required for a public purpose.

In Head, Transport for Victoria v Kilpatrick & Anor [2024] VSC 686, TfV challenged the Tribunal’s decision in the Supreme Court. In a complex and lengthy decision, handed down almost 18 months after the last hearing day, the Court dismissed the appeal. It made some interesting remarks about the Applicant’s case, including:

…. I put to senior counsel for the statutory authority that large parts of his case seemed to assume that test or token applications were illegitimate and that applications of that nature should be dealt with as though they were not of that nature. In response, he expressly acknowledged that he would need leave to further amend the amended notice of appeal to warrant an attack on the legitimacy and effectiveness of test or token applications and that he would need instructions before applying for such leave. After obtaining instructions, he expressly declined to seek such leave. On the other hand, in a self-contradictory fashion, the statutory authority still persists with all of its original arguments in this Court, including all those arguments which assume, wrongly, that test or token applications are illegitimate or ineffective, or should be dealt with as though they were not of a test or token nature. This is a major weakness in the statutory authority’s case. [8]

The Court summarised its main conclusions as follows:

  • although it is true that VCAT had only review jurisdiction in this matter, VCAT was well aware of that and did not purport to exercise any original jurisdiction;
  • in any event, VCAT’s decision and order was of a kind available to it in the proper exercise of its review jurisdiction;
  • VCAT did not omit to take any steps required of it in the proper exercise of its review jurisdiction;
  • VCAT did not fail to take into account any obligatory considerations;
  • VCAT did not arrive at any findings that were not open to it in the circumstances; and
  • that there was nothing irrelevant (or otherwise inappropriate) about VCAT’s finding that the statutory authority had not come to VCAT with clean hands.

Whilst granting leave to appeal but dismissing the appeal, the Court accepted that the prospects of success of the proposed appeal could be described as better than ‘fanciful’, albeit only barely.

See also: 

  • Guide to Planning Appeals: Compensation

5. Is the requirement to pay for a roundabout duplicating a DCP requirement?

In DFC (Project Management) Pty Ltd v Baw Baw SC [2024] VCAT 1099, the Permit Applicant contested a number of conditions on a permit for residential estate comprising 382 lots, a primary school, community facility and commercial land uses.

One set of the contested conditions related to the construction of a roundabout. The conditions were imposed by the Department of Transport and Planning in its role as a referral authority. Council supported the conditions.

There was also a separate condition requiring the payment of levies for items in the Development Contributions Plan (DCP), which includes the roundabout.

The Applicant was concerned that the conditions would result in double-dipping, which the Tribunal has held in a number of cases to be an unacceptable outcome. Cases include Carson Simpson Pty Ltd v Casey CC [2006] VCAT 1725, Dennis Family Corporation v Casey CC [2006] VCAT 2372 and Holner Pty Ltd v Baw Baw SC (Corrected) [2020] VCAT 890.

However, the Tribunal considered there was a complication which prevented it from applying the principles found in the above cases, as well as the Supreme Court case Casey City Council v Carson Simpson Pty Ltd [2007] VSC 25. This complication is due to the conditions being required by a determining referral authority, as distinct from the Council.

The Tribunal concluded that the conditions have the potential to result in an outcome that is unreasonable and inequitable for the Applicant on the basis of:

  • the conditions are not clear whether they require the construction of the roundabout in accordance with the DCP or require some alternative – this condition has been written vaguely;
  • it is the role and responsibility of the Council as the developing agency under the Drouin DCP to construct the roundabout using the funds it already has at its disposal, and it would be unfair and inequitable to move that responsibility to another party;
  • there is a level of unfairness associated with requiring the applicant to both make the contributions under the Drouin DCP, and undertake the works to be funded by those and other contributions; and
  • the need for this roundabout is not primarily created by the levels of traffic anticipated from this approved subdivision, but rather is primarily driven by the growth in traffic from other parts of Drouin.

Whilst the Tribunal noted that the Council intended to address the fairness issue via offsets and credits for the cost of the construction, it considered it cannot address the cost of finance to fund the works until such time as the offsets and credits are granted, and it cannot address the time required to be invested by the Applicant in managing the construction of the infrastructure.

See also:

  • Guide to Planning Appeals: Conditions > Validity of conditions

6. When you forget to apply for a car parking reduction

In Tsourounakis v Cardinia SC (Red Dot) [2024] VCAT 1104, application was made to amend an existing permit for an education centre to increase the number of students from 16 to 60.

Under Clause 52.06-3, 18 car parking spaces would be required (4 were already provided on site). However, no application had been made to seek a dispensation of car parking spaces.

The Tribunal noted that Form 4 of the Planning and Environment Regulations 2015 requires all permissions granted to be included on the permit. Whilst Council submitted that the wording of condition 3 can be amended, the Tribunal found that in this instance, the scope of any such amendment is more limited than what the Council submitted. It stated:

In this case, the applicant has sought to amend the wording of condition 3. But that amendment goes beyond what the limits of section 51(2)(b) enable as it applies to a section 80 review, in my view. 

Any variation to a decision in a section 80 review pursuant to section 51(2)(b) must be related to the permissions ultimately granted. This is because the permit has already been granted, and the considerations of the acceptability of a proposal based on the permissions triggered, have already been considered.

Introducing new permit triggers in addition to the permissions that have already been granted is beyond the scope of a section 80 review, having regard to the powers conferred on the Tribunal under section 51(2)(b). 

This same logic applies to the deletion of a condition and inclusion of an alternative in its place, if that alternative is not related to the original condition or is unrelated to the permissions granted. [49-52]

The Tribunal considered the case is fundamentally different to cases that have addressed this issue, because the consequences of variations to conditions sought were within the scope of what the permit already allowed. These cases include Bread of Life Church (Melbourne) Inc. v Whitehorse CC [2018] VCAT 1751 and CMA Corporation Pty Ltd v Maroondah CC [2010] VCAT 660.

The case was summarily dismissed the application under section 75 of the Victorian Civil and Administrative Act 1998. Back to Square 1 for the Applicant.

See also: 

  • Guide to Planning Appeals: Permit > Amendment to permit > new permit trigger

7. A missing transcript and implications at judicial appeal

In AVC Operations Pty Ltd v Maribyrnong City Council & Ors [2024] VSC 683, the Supreme Court dismissed an appeal, and refused to grant leave.

The decision is important because it may inform whether parties seek an assurance that transcript is available during a hearing before the Tribunal, and elect to appeal in circumstances where there is documentary support behind any alleged jurisdictional error.

The Tribunal refused to grant an amendment to a permit for an expansion of a beer garden based upon concerns about the risk of flooding. The garden area concerned was subject to a Land Subject to Inundation Overlay. The hotel enjoyed existing use rights, as the hotel had been in continuous operation since the 1870s.

The amendment application lodged with the Council, sought first to expand the larger terrace authorised by the permit and secondly, to increase the area in which liquor could be sold and consumed and increase the patron numbers permitted on site.  Melbourne Water objected to the amendment based upon the high risk of flooding.  Melbourne Water also found that the ‘proposed building structure for the new serving/bar, cool room and toilets are not in compliance with the minimum finished floor level requirements’ under the Guidelines for Development in Flood Affected Areas, which require that new buildings be a minimum of 600mm above the applicable flood level.

The Council failed to decide the application within time and the Permit Applicant filed an application for review under section 79 of the Planning and Environment Act 1987 (P&E Act) in the Tribunal.

If the Council had made a decision within the statutory time frame, it would have been required by section 61(2) of the P&E Act to refuse the amendment application by reason of Melbourne Water’s objection.

In Phelan v Port Phillip CC [2023] VCAT 376, the Tribunal found that where land used for a hotel enjoyed existing use rights, no permission was required under the planning scheme to increase patron numbers or increase the area in which alcohol was sold or consumed.  Accordingly, the Permit Applicant amended their grounds of review, removing the application for permission under Clause 52.27 of the Scheme and reducing the proposed beer garden from 698 square metres to 571 square metres.

Following a hearing of five days, the Tribunal found that the amendment should be refused for reasons relating to the high risk of flooding.  The key issues were: whether increased flooding risk would flow from the proposed extension to the beer garden; and whether the flooding risk mitigation measures proposed were acceptable.

The Court summarised the Tribunal’s determination at [20] as follows:

The Tribunal concluded that there would, if the extension was approved, be a potential increase in patrons in the beer garden of 656 patrons, which meant that there would be an increased population at risk from the existing flood hazard. The Tribunal did not accept that an increased population at risk was acceptable because it arose in the context of an existing use. It interpreted the Planning Scheme and flood management policy and guidelines as requiring that proposed density increases be assessed very carefully in high risk areas, and that risk must be avoided and minimised if possible. The Tribunal found that the mitigation measure of evacuation relied upon by AVC in its Flood Risk Management Plan (FRMP) ‘being one of the lowest approaches on the hierarchy of flood risk management’, was not adequate. It concluded that AVC’s proposal did not respond appropriately to the degree of risk and that no permission should be granted under the LSIO, with the consequence that the Amendment Application must be refused. [Citations omitted]

In the appeal, the advocates before the Tribunal each filed affidavits as to the submissions they made, because the transcript of hearing was unavailable.  There was no recording of transcript due to a technical error.  A request for the notes of the presiding members was refused.

The Court determined that the scope of the argument presented before the Tribunal was not as wide as the Appellant contended in the appeal.  Moreover, the Court found that the appeal did not have a real prospect of success and refused to grant leave to appeal.

The Court emphasised the need to appreciate — in assessing whether submissions to the Tribunal are sufficiently substantial and clearly articulated — that the first ground of review is a species of constructive failure to exercise jurisdiction, or of failure to accord procedural fairness. Only substantial arguments, clearly put to the Tribunal, will have the effect that the absence of consideration by the Tribunal in its reasons leads to a failure to exercise its jurisdiction.

The Court concluded that the argument put to the Tribunal did not involve the clear articulation of the “risk comparison argument”. As a whole, the submissions and evidence did refer to the present ‘scope to accommodate more patrons within the existing beer garden and buildings’, subject to the only constraint being the liquor licence, which was in turn driven by physical capacity. However, there was no submission that this potentially created a risk which the Tribunal was required to consider and balance against the risk arising if the Amendment Application was granted and a flood risk management plan (FRMP) required.

From this, the Court concluded that the Tribunal’s reasons were adequate.

The Court found that each of the three grounds advanced by the Appellant had no prospect of success.  To the extent that submissions were made that any comparison was called for, this was not done in a way which made it clear that it was a substantial part of the Permit Applicant’s case, nor was it clearly articulated. Further, the Permit Applicant did not make available to the Tribunal any evidence or other material which would have made such a comparison meaningful or appropriate.  There was no jurisdictional error because the Permit Applicant did not support any such submission with evidence or information which would have made it possible for the Tribunal to make that assessment comparing risk mitigation measures.  That is, a comparison between the risk of an increase in patron numbers (people present on the land) under the permit application with risk mitigation controls compared to the existing risk, which included the possibility of an increase in patron numbers beyond the remit of the planning system and therefore not subject to the permit application process.

Further arguments were similarly considered and dismissed and leave to appeal was refused.  The Court found that the argument, even if it had been put to the Tribunal, was also not based on established facts, nor supported by evidence or material which would have enabled the Tribunal to find facts for the purposes of assessing the argument.  At best,

the appeal concerned a complaint as to how the Tribunal considered and determined the argument.

Your editors note this case highlights the difficulty for an appellant that seeks to persuade the Court that there has been a jurisdictional error by the Tribunal in circumstances where it seeks to rely on oral submissions that are not clearly stated in the notes of counsel or written submissions, or evidence, and where transcript is unavailable.

The Court’s reasons are lengthy and detailed concerning each of the three grounds, which were rejected.

Your editors also note that it is somewhat unusual for leave to appeal to be refused by the Court, in circumstances where each party is represented.  The refusal of leave suggests that the Court takes a dim view of appeals based upon jurisdictional error where there is no documentary record of the arguments that were put, and no supporting evidence concerning any such arguments. It may be prudent to canvass with a transcript provider whether transcript is available at the start of a hearing even if it is not ordered (and paid for) until the conclusion of the hearing.  In this way, technical errors in transcript may be more likely to be identified before it is too late.

See also:

  • Guide to Planning Appeals: Appeals > Transcripts