VCAT Volume 12 No 10
1. The final dance: Dance proceedings come to an end
We have commented on the various Dance v Colac Otway SC proceedings in previous editorials, including at VCAT Vol 11 No 11 and VCAT Vol 12 No 6.
It may be recalled that in Dance v Colac Otway SC [2024] VCAT 443 the Tribunal issued an Interim Order that supported a proposed tourist accommodation (Group accommodation and Caretakers dwelling) pursuant to permissions under the Rural Conservation Zone (RCZ) and the Significant Landscape Overlay (SLO). The Interim Order required changes to be made to the plans.
Because the required changes to the plans could potentially impact on matters under the Erosion Management Overlay (EMO) and the Bushfire Management Overlay (BMO), matters which were not within the Tribunal’s jurisdiction having regard to Myers v Southern Grampians Shire Council [2023] VSC 658, the Interim Order required the Responsible Authority to advise the Tribunal and the other parties of the decision (including the permit conditions if a permit is to issue) it had made relating to the amended permit application (to be lodged by the Respondent permit applicant) pursuant to the EMO and the BMO.
However, the Interim Order was not able to be acted upon as envisaged because there were further changes to the plans.
It may also be recalled that in Dance v Colac Otway SC (No. 3) [2025] VCAT 52, the Respondent permit applicant advised the Tribunal at a Practice Day hearing it has since gained conditional support from the CFA under the BMO and support from Council for planning permission to be granted under both the EMO and the BMO. The support from both authorities required further amended documents and amendments to the proposal, being amendments made to the VCAT substituted amended plans and documents.
The Tribunal decided to the best way forward was to invite the Council to reconsider its decision.
In Dance v Colac Otway SC (No. 5) [2025] VCAT 437, the Tribunal considered the final set of conditions provided by Council following the Tribunal’s invitation to consider the application as a whole. There were two conditions in the original Notice of Decision that were disputed by the Respondent permit applicant in the first three hearing days. Council decided not to impose these conditions in its new decision. The objector Applicant requested that these two conditions be included in the permit. The final hearing day and the final decision by the Council considered the submissions made about these conditions (which concern a section 173 Agreement alerting future owners to the land management plan and potential need for further landscaping). The Tribunal declined to include these conditions in the permit.
The Tribunal reflected on the challenging issues that needed to be addressed where the Tribunal has limited jurisdiction in the one application. It stated:
There are benefits in an omnibus planning application and consequential permit. An omnibus permit is what was sought by the Respondent permit applicant and that is what Council decided to grant. As the Tribunal does not have jurisdiction over all of the planning permissions in this omnibus planning application, the process has been complex. The necessity for a process such as this has not changed in the time we have been dealing with this proceeding (i.e. the extent of Tribunal jurisdiction has not changed). This means this situation is likely to arise again in the future. We hope the experiences learned by the Tribunal and the parties in this proceeding may assist in any future review applications that require a similar process to facilitate an outcome in the form on an omnibus permit. [9]
It then made two suggestions that may assist to make the necessary process more efficient if this circumstance arises again in another proceeding:
- The ability to retain some involvement from a relevant referral authority (such as the CFA where planning permission is required under the BMO) as ‘a friend of the Tribunal’ can be useful; and
- The ability to utilise the remittal power under section 51(A) of the Victorian Civil and Administrative Tribunal Act 1998 can enable a Council to bring all the planning permissions in an omnibus application back together when there are differing versions of plans and documents between the various planning permissions that are before both the Tribunal and Council.
Another issue that is worth exploring in your editors’ view are the implications of third party objection and appeal rights when parts of applications are exempt. This scenario raises complex legal issues and raises concerns about the complexity of the planning system, making it more alien to non practitioners than it needs to be.
The current review of the Planning and Environment Act 1987 provides the opportunity to address the Tribunal’s suggestions.
See also:
- Guide to Planning Appeals: National Trust principle
2. Consent for a City Road swingers club
Third party objectors challenged a decision of the Council to approve an adult lifestyle meeting place in Baenziger v Port Phillip CC [2025] VCAT 375.
The proposal was described as an adult lifestyle meeting place that includes live music entertainment and the sale and consumption of liquor. The venue allows sex on premises in a consensual manner between patrons. The venue is to be open to the public, but requires ticketed entry.
There were some concerns about the exact nature of the use. The Tribunal distinguished the use from a Sex services premises, which is defined as:
Land used to sell services involving the use or display of the body of the person providing the service for the sexual arousal or sexual gratification of another person while they are present on the land. (Tribunal emphasis)
It does not include:
-
- Live entertainment performed for an audience, by a person performing an act of an explicit sexual nature, such as lap dancing, nude dancing and striptease.
- Sexual activities engaged in by two or more people required to pay an admission fee or charge to enter the premises on the same terms and who do not receive any form of payment or reward, whether directly or indirectly, for engaging in the sexual activities.
The Tribunal was satisfied that what was advertised to the community was sufficiently clear as the notice referred to the application documents that provided further detail as to the premises operations. However, the Tribunal considered a permit condition providing clearer understanding of the use was appropriate. The Tribunal proposed to amend conditions to include references to the activities of a Use of a sex on premises venue (SOPV), as identified in the scheme, and the associated activities proposed at the venue.
Concerns were also expressed that if there is insufficient room for the proposed number of patrons, particularly for the proposed activities of the venue, it may lead to adverse off-site amenity and safety concerns. Specifically, it was submitted that patrons, particularly ‘young males’, may end up ‘leaving the premises, unsuccessful’ due to the number of people on-site relative to the rooms and areas provided for the uses. The Applicant submitted that the potential implications of this are that there is likely to be a significant group of dissatisfied customers on any night who may leave the venue and cause safety concerns in the community. In addressing these issues, the Tribunal stated:
We do not concur with submissions of the applicant that the floor area for the proposed uses, relative to the proposed patron numbers, leads to patrons potentially leaving the venue ‘unsuccessful’. Nor was any evidence presented to us that if a patron is ‘unsuccessful’ that there is a clear link that it will lead to an unreasonable public safety issue. This is noting that in assessing the proposal the council notified Victoria Police of the proposal, and no objection was received as a result of this notice.
We also note the draft venue management plan, included as part of application material, has a requirement that patrons must pre-book so that patrons can be advised before they enter of what to expect on-site, and the venue rules. [46-47]
The Tribunal went on to say:
Nor is it our role to make moral judgement on the quality of patrons who can or should attend the venue. These are matters outside the ambit of our discretion that we are required to exercise and consider under the scheme provisions that apply. We reiterate comments of Hunt Club Commercial Pty Ltd v Casey CC (Includes Summary) (Red Dot), [2013] VCAT 725 as referred to us:
[15] Town planning is not a panacea for all perceived social ills, nor is planning decision-making a forum for addressing all issues of social or community concern. … Town planning does not involve itself in moral judgements nor, subject to this locational or spatial perspective, in the operation of a competitive market economy in which certain goods and services are lawfully made, sold or consumed. Whilst town planning seeks to secure a pleasant, efficient and safe working, living and recreational environment, it is not the role of town planning to address all issues of public health, nor to regulate the pricing or general availability of a product to manage the health and well being of a society.
In granting a permit, the Tribunal was satisfied that with a number of management measures in place the venue can operate in a reasonably safe and amenable manner in context of its physical location.
See also:
- Guide to Planning Appeals: Adult lifestyle meeting place
3. Are the Clause 54 requirements relevant to a permit required under the Neighbourhood Character Overlay?
In Rodgers v Port Phillip CC [2025] VCAT 385, the Tribunal considered two questions of law as follows:
- Does the Neighbourhood Character Overlay (NCO) at Clause 43.05-3 of the Victorian Planning Scheme (VPS) require the decision maker to broadly consider Clause 54 of the VPS?
- What is the legal meaning of ‘reinforce’ in the context of the Port Phillip Planning Scheme NCO?
The proposal involved the partial demolition, alterations and additions to a double storey townhouse.
On the first question, the Tribunal considered there is no doubt that Clause 54 is a relevant document to this permit application, however the real question is which of its provisions are invoked or ‘applicable’ to the discretion to be exercised under NCO5.
The Tribunal considered that the only reference to Clause 54 provisions in Schedule 5 to the NCO is in the table in Clause 4.0 which contains modified standards. It held that it is significant that in the absence of this provision, there would be no reference to Clause 54 in the overlay provision itself.
As to the modified standards in the NCO, the Tribunal preferred the view that other objectives of Clause 54 could be considered if specifically relevant to the purpose of NCO5 is to ‘do as little harm’ to the application provisions of Clause 54 as stated, while maintaining its lawful scope of operation in applications under NCO5.
By contrast, it is not necessary or appropriate to consider other remaining objectives and standards of Clause 54 when evaluating a proposal under NCO5 where those standards have not been enlivened under the overlay – either by way of modification or by demonstrated relevance to its purpose. It stated that this “is consistent with a purposive reading of the NCO as a bespoke overlay control that focuses on neighbourhood character.”
Alternatively, the Tribunal considered it would be inconsistent with the purpose of the control to seek to expand the scope of NCO5 to include the full range of objectives and standards provided in Clause 54.
Reference was made to two Tribunal decisions where different approaches had been taken, Adams v Glen Eira CC [2016] VCAT 1353 and Gian v Glen Eira CC [2018] VCAT 317.
In Adams, the Tribunal took a purpose-driven interpretation of Clause 54 in light of the NCO as the control under which permission was required.
In Gian, the Tribunal answered the question primarily by reference to the content of Clause 54 itself and noted there was no express direction in the NCO to exclude certain standards of Clause 54.
Having regard to these two cases, the Tribunal stated:
Having regard to the legal scope of the discretion to be exercised in this case, I prefer the outcome adopted by the Tribunal in Adams, since the starting point for interpreting the planning scheme as subordinate legislation is a consideration of the words of the NCO and Schedule 5 in their context; since this control is the source of the permit requirement for this proposal.
For this reason, I find it is not appropriate to start with an analysis of the wording of the provisions in Clause 54, standing alone.
Clause 54 is only brought into play by the NCO in this instance and its operation is governed by the extent of the primary enabling control. In this instance, matters other than neighbourhood character are excluded.
I accept that this conclusion would likely result in a case-by-case analysis of which standards (and objectives) of Clause 54 should apply in addition to the modified provisions within the schedule where the only permission is under the NCO.
This would detract from the more recent state government approach to planning scheme amendments to seek to provide greater certainty to applicable standards and objectives. [125-129]
Recognising the complexity of the task in statutory interpretation, the Tribunal stated that it may be desirable for the provisions of the NCO or relevant schedules to be clarified as to which any other provisions of Clause 54 apply (if any), in addition to those which are expressly modified.
The Tribunal also noted that the Tribunal and Supreme Court have confirmed that the extent to which matters in Clause 65 will be ‘appropriate’ to any given application will depend on whether those matters are relevant to the particular discretion to be exercised under the primary control.
On the second question on the legal meaning of ‘reinforce’ in the context of the Scheme, in applying the ordinary meaning of ‘reinforce’ to strengthen, bolster or support something, the Tribunal held there is no prescription in the planning scheme that each objective within an overlay must be satisfied in order for a permit to be granted, neither is there an indication in the provisions of the overlay that each objective is to be weighted equally.
As to the merits of the proposal, the Tribunal concluded that the proposal will not adversely affect the unique and clearly identifiable character of this precinct that contains two-storey attached and detached houses within a landscaped setting.
See also:
- Guide to Planning Appeals: ResCode
4. Is a failure to provide a residential use in an Activity Centre contrary to policy and an underdevelopment?
In Fabcot Pty Ltd v Maribyrnong CC [2025] VCAT 378, the Tribunal considered a refusal for the Use and development of the land for a supermarket, retail premises, child care centre, office including medical centre and leisure and recreation centre and the sale of packaged liquor.
The subject site is located in the West Footscray Neighbourhood Activity Centre (WFNAC) in the Mixed Use Zone. Three overlays also apply to the site, including a Design and Development Overlay.
Three permits had previously been granted at the direction of the Tribunal, including a five storey building with basement carparking comprising 111 dwellings.
With respect to the lack of residential use, the Tribunal stated:
We are not persuaded the lack of residential use is unacceptable. Amongst other things, the purposes of the MUZ and relevant policy set out in the Planning Scheme seek to encourage the provision of residential land use in the proposed location and within the activity centre. However, whilst the policy settings encourage the provision of residential land use, we do not find that it means that every site must accommodate housing.
The Planning Scheme encourages residential development at upper levels. While there is policy support for residential uses we do not consider the proposal would undermine the planning of the activity centre so as to make it unacceptable, noting a mix of commercial uses that are acceptable in an activity centre are proposed. [52-53]
With respect to underdevelopment, the Tribunal stated:
We have been persuaded that the proposal is not an underdevelopment of the site. For the reasons previously discussed we do not find that incorporation of a residential use is essential to make the proposal acceptable. Similarly, we are not persuaded that the proposal must have a taller built form to be acceptable. A greater form of development is possible however we are persuaded by the applicant the 11.38 metre height of the building albeit at two storeys in scale is an acceptable response from a built form perspective. Whilst the built form is less than the preferred height of 16.5 metres, we find the massing and form of the proposal is an acceptable response to the preferred height. [66]
The Council was also concerned that the proposal will have an unacceptable impact on the WFNAC and relied on an economic analysis report that finds that the impact on the activity centre is the likely closure of some of the existing retailers including the IGA supermarket and that the self-contained design of the proposal at the western end of the activity centre will increase the risk of disconnection from the retail core. The Tribunal stated:
We have not been persuaded that the closure of the IGA is a forgone conclusion however in any competitive market the possibility of closure or a repositioning to an alternative offer exists. In the event the extent of impact on the IGA result in a change, based on the economic evidence we are satisfied that the WFNAC will continue to be viable and the community will continue to be served by a supermarket. In this context whilst we accept that there will be a trade impact on the IGA, we are not persuaded that the extent of impact and the potential outcome of the impact on the IGA means the proposal is unacceptable. [104]
Whilst the Tribunal must decide each case on its merits, the Tribunal’s findings in this case appear to run contrary to other cases concerning underdevelopment, noting that in particular a previous approval for 115 dwellings on the subject site. The decision also seems contrary to recent state government changes to activity centre plans and controls that seek to maximise development opportunities. However, having said that, there are no explicit provisions in the new activity centre controls that require consideration of underdevelopment. This seems to be a serious shortcoming of the new activity centre provisions.
See also:
- Guide to Planning Appeals: Supermarket, Underdevelopment
5. Rejection of application under VicSmart
As practitioners are well aware, VicSmart was introduced into the Victoria Planning Provisions to fast-track minor applications.
In Harrison v Nillumbik SC (Corrected) [2025] VCAT 413, there was a dispute as to whether an application to consolidate three sheds into one shed could be considered under the VicSmart provisions.
The Applicant argued that Clause 35.06-5 in the Rural Conservation Zone is the ‘primary control’ and there is no need for the Bushfire Management Overlay (BMO) to refer back to the VicSmart application process because the ‘necessary entry point’ for that process already exists through Clause 35.06-5.
Further, it was argued that the requirement for a permit under the BMO is not the ‘primary trigger’ for the application – it is a ‘secondary control’ and it does not nullify or override the VicSmart ‘eligibility’ provided by Clause 35.06-5.
The Council submitted that because the requirement for a permit for the construction of buildings and works involved in the proposed development under the BMO is not expressly identified in Clause 44.06-2 as a class of VicSmart application, the permit application cannot be processed as a VicSmart application.
In declaring that the application was not a VicSmart application, the Tribunal held:
- Properly characterised, the permit application in this matter is an application for three separate permits under the planning scheme; separately under Clause 35.06.5, Clause 42.01-2 and Clause 44.06-2;
- An application that seeks a permit under more than one clause of a planning scheme is commonly referred to as an omnibus application even though that expression does not appear anywhere in the Planning and Environment Act 1987 (P&E Act) or in planning schemes;
- There is nothing in either the P&E Act or the planning scheme that elevates the requirements of a zone to the ‘primary control’ applicable to use or development of land. To the contrary, Clause 71.04 of the planning scheme makes it clear that the provisions of an overlay apply in addition to the provisions of the applicable zone and any other provision of the scheme.
The Tribunal referred to the Victorian Court of Appeal Sweetvale Pty Ltd & Anor v Victorian Civil and Administrative Tribunal & Ors [2003] VSCA 83 decision, which confirmed that section 47(1) of the P&E Act plainly and clearly contemplates that an applicant for a permit may lodge a single application for a permit for use or development for a combination of use(s) or development(s).
Further, the Victorian Court of Appeal in Boroondara City Council v 1045 Burke Road Pty Ltd [2015] VSCA 27, held that a single permit for an overall development proposal cannot be granted unless the responsible authority considers each permit requirement that applies to the proposal and would grant a permit in relation to each such requirement.
Given there are three distinct and separate permissions required for the shed proposal, each must be considered against the requirements of the control under which the obligation to obtain a permit has arisen.
See also:
- Guide to Planning Appeals: VicSmart
6. Policy considerations scuttle changes to nightclub operation
In careful analysis of State and local policy, the Tribunal in Purcell v Darebin CC [2025] VCAT 398 set aside Council’s approval to increase the number of patrons and increase the hours of operation of an existing nightclub in a neighbourhood activity centre. There were a number of nearby residents who objected to the application and challenged Council’s decision.
Having regard to the policy setting, the Tribunal stated:
I have considered these policies and applied them to the subject land’s context, i.e. its location in the High Street strategic corridor and Westgarth Village neighbourhood activity centre. These policy settings call for a balancing of local community needs for entertainment venues such a bar with the needs for a reasonable level of amenity that align with the role and function of a neighbourhood activity centre. While I accept that High Street corridor is a busy inner urban area, the location for late night attractions is directed by policy toward major activity centres, rather than this neighbourhood centre. This is a readily distinguishable feature of this proposal when compared to the likes of that considered in The Terminus Hotel proceeding (The Terminus Hotel (FHG) Pty Ltd v Yarra CC [2023] VCAT 1068) which was referred to by the council during the hearing.
I conclude from the balancing of the policy settings that there is little strategic support to ‘enliven’ the Westgarth Village neighbourhood activity centre by way of late-night operations of a bar beyond that which may serve local community needs and would present risks of adverse impacts to the level of amenity expected for such a lower-level activity centre. [54-55]
See also:
- Guide to Planning Appeals: Nightclub
7. Does the planning scheme regulate helicopter flight paths?
In Afonso Building Solutions Pty Ltd v Wodonga CC [2025] VCAT 430, the Tribunal considered an appeal against the Council refusal for a helicopter landing site. The application was made by a building construction company.
The subject land is in the Commercial 2 Zone (C2Z) and in a Development Plan Overlay. Permit triggers exist under the C2Z and Clause 52.15-1, Helicopter Landing Site.
Council’s ground of refusal were:
- The proposal is not generally in accordance with the White Box Rise Development Plan.
- The proposal does not meet the decision guidelines in Clause 52.15-3 in relation to amenity and nearby sensitive uses.
- The proposal will have adverse effects on community amenity from noise and is not consistent with Clauses 13.05-1S, 34.02-2 and 34.02-7 of the planning scheme.
- The proposal will have unacceptable safety impacts in terms of driver distraction and does not meet Clauses 02.02, 18.01-1S, 18.01-3S and 65.01 of the planning scheme.
- The proposal will have an unacceptable impact from dust on nearby land use and does not meet the decision guidelines in Clause 34.02-7.
- The number of objections gives rise the consideration of whether the proposal may have a significant social effect.
At the commencement of the hearing the Applicant sought to amend the application, including Introduce a preferred flight path plan. However, in relation to this matter the Tribunal stated:
Helicopter flights paths are not regulated by the Wodonga Planning Scheme (‘planning scheme’), and while the flight paths proposed might be the logical routes for helicopters coming and going, there is no relationship to the approval of the helicopter landing site itself. I thus do not consider it appropriate to include the flight paths as part of the assessment of the application before me. At its simplest, if the flight path map is included as part of the endorsed plans but helicopters use different routes, in my view there is no capacity within the planning scheme for council to enforce such a ‘breach’. [6]
The application received 123 objections. However, the application is exempt from notice under the planning scheme and was erroneously advertised. Despite this, Council took into account the objections in deciding to refuse the application. The Tribunal stated:
The giving of notice when it was not required appears to have generated significant community concern about a small-scale helicopter landing site with ten movements a week (now six). Where the issues raised in those objections are relevant to the grounds pursued by council and are matters that the planning scheme requires to be considered I have addressed them. [61]
See also:
- Guide to Planning Appeals: Helicopter landing site
8. Landscape impacts of a private basketball court
Retrospective approval was sought for a basketball court on a site constructed with a private dwelling in Sui v Whitehorse CC [2025] VCAT 381. Council had refused the application because the court is inconsistent with the tree-dominated landscape, bush environment character and the very special landscape qualities of the Significant Landscape Overlay (SLO).
The court required a permit under the SLO because of the extent of its hard surface. Under the SLO2, a permit is not required to construct a building or construct or carry out works if hard surfaced and impervious areas (including tennis courts and swimming pools, but excluding buildings) are less than 17% of the site area; and if the total area of all buildings and hard surfaced and impervious areas (including tennis courts and swimming pools) are less than 50% of the site area.
A permit was triggered because the proposal resulted in:
- 84% of the subject site (above the 17% requirement), or 32.4m2 of land, being covered by hard surface or impervious areas; and
- 5% of the subject site (above the 50% requirement), or 16.9m2 of land, being covered by hard surface, impervious areas or buildings.
In setting aside Council’s refusal, the Tribunal was satisfied the proposal maintains an inconspicuous profile and does not dominate the landscape, particularly given that the existing character of the immediately locality. It also noted the basketball court provides for an open space use as anticipated by the SLO.
Though not explicitly stated, perhaps due to planning relevance, no doubt the health benefits of providing an active recreational facility that only breached the siting requirements to a minor degree is an argument in favour of the court.
See also:
- Guide to Planning Appeals: Landscape impacts