VCAT Volume 11 No 6
1. Be careful for what you wish for: referral authority not able to provide referral comments
Amendment VC85 to the Campaspe Planning Scheme introduced an update of the Campaspe Local Floodplain Development Plan (LFDP) as an Incorporated Document in 2010. The LDFP operates in the same way as the various Victoria Planning Provision flood controls, such as the Land Subject to Inundation Overlay (LSIO). Proposals which require a permit, and which are consistent with the LFDP, are not referred to the relevant Catchment Management Authority, unless in the opinion of the responsible authority the proposal does not satisfy the requirements or conditions of the LFDP.
One of the main purposes of the use of an Incorporated Document, as articulated in the explanatory report prepared for the planning scheme amendment, was to streamline the planning system by avoiding referrals.
In Cinanni v Campaspe SC [2023] VCAT 797, a Practice Day hearing was held to consider, inter alia, whether the objection from the North Central Catchment Management Authority (NCCMA) to an application for 16 dwellings should be summarily dismissed.
The review site had been subject to flooding most recently in October 2022. Whilst Council had made the NCCMA aware of the application, it did not refer the application to it pursuant to Clause 66.03 of the Planning Scheme. The Council delegate held that the proposal met the requirements of the LFPD on the basis that the finished floor levels were 300mm above the 100-year ARI flood level, amongst other matters.
Notwithstanding, the NCCMA noted in their objection to Council that in the current Echuca Moama Flood Study preliminary information had indicated slightly higher flood levels at the site subject to the application for permit.
At the Practice Day hearing, the NCCMA argued that if it has standing, then the Tribunal has jurisdiction to hear the application under section 82AAA of the Planning and Environment Act 1987 (P&E Act). This involved findings in relation to jurisdictional facts.
On the jurisdictional facts, the Tribunal held:
- The NCCMA was not a recommending referral authority for the purposes of the proposal at the time of the application because the Council formed the opinion that the proposal satisfied the requirements or conditions of the Campaspe LFDP, meaning that referral was not required under Clause 55 of the P&E Act; and
- Whilst the NCCMA lodged the NCCMA objection with the Council, it did not and could not have done so as a recommending referral authority.
As such, the Tribunal found that the application could not be brought under section 82AAA because this section can only be brought by a recommending referral authority.
In the alternative, the NCCMA sought to convert its application to an application brought under section 82 of the P&E Act. However, the Tribunal considered that the permission sought under the LSIO is not available for review under section 82 on the basis of the third party objection and appeal rights under the LSIO. This is similar to the issues in Clifftop at Hepburn Pty Ltd v Hepburn SC [2023] VCAT 201.
Overall, the Tribunal found:
If I was to exercise my discretion to allow the application to be converted to one brought under section 82 of the Act, it would need to be on the basis that flooding issues were not raised by the NCCMA. In the circumstances of what is the entire focus of the NCCMA Objection, the NCCMA’s grounds of review and its submissions to the Tribunal, I regard this to be implausible. Even the first two grounds of review that raise the Council’s key strategic directions and the natural hazard State planning policy do so in the guise of dealing with flooding concerns. [275]
The Tribunal also held for the same reasons that third party objections from local residents on flooding grounds could not be considered, and their applications on such grounds were also summarily dismissed.
It is understood that following the October 2022 Victorian flood event that a number of flood studies are being undertaken. Given the nature of the event, it does not surprise that the studies may find more properties at the risk of increased flooding. Under such circumstances, it can be argued that the NCCMA, concerned about increased flooding on the subject property, had adopted an appropriate precautionary approach in its ‘objection’ to the proposal. However, because of the motivation to streamline the planning system, approved through a planning scheme amendment, it has been formally excluded from the process. It will be interesting to see whether the CCMA will support similar exemptions in any future planning scheme amendments that introduce updated flood controls in the planning scheme.
See also:
- Guide to Planning Appeals: Flood risk
2. Is a Notice of Decision a ‘statutory authorisation’ under the Aboriginal Heritage Act?
In Hanson Construction Materials Pty Ltd v Greater Bendigo CC (Corrected) (Red Dot) [2023] VCAT 1341, a preliminary hearing was held to determine whether a Cultural Heritage Management Plan (CHMP) was required for a three lot subdivision and the construction of a dwelling on each lot.
The permit applicant submitted the Notice of Decision granted by Council is not a statutory authorisation because it is not a permit, but is a mere intention to grant a permit if there is no review application lodged under section 82 of the Planning and Environment Act 1987 (P&E Act).
Under sections 51 and 52 of the Aboriginal Heritage Act 2006 (AH Act), if a sponsor proposes to carry out an activity for which a CHMP is required and if a statutory authorisation is required before the sponsor can carry out the activity, the relevant decision maker must not grant a statutory authorisation unless it receives an approved CHMP for the activity. Section 50 of the AH Act states that a statutory authorisation is ‘a permit under the under the [P&E Act] to use or develop land for all or part of an activity’.
The Tribunal considered there were a number of reasons why a grant of a permit under section 61 must be a statutory authorisation:
- The reference to ‘the grant’ of a statutory authorisation in section 52(1) of the AH Act must be a reference to the grant of a permit under section 61 of the P&E Act. This follows from the statutory interpretation principle that in the absence of any context indicating a contrary intention, the legislature must be presumed to attach the same meaning to the same words when used in a subsequent statute in a similar connection.
- The AH Act does not evince an intention (and nor does any provision of the P&E Act enacted after enactment of the AH Act evince an intention) that ‘grant’ means anything other than grant under section 61 of the P&E Act.
- The language in section 52(4) is consistent with a conclusion that the decision to grant under section 61 is a statutory authorisation. Section 52(4) provides that ‘if the decision maker is required to decide whether to grant the statutory authorisation within a certain period’, that period does not commence until the decision maker has received an approved CHMP. This must be a reference to the grant of a permit under section 61 of the P&E Act because there is no ‘period’ specified for issue of a notice of decision following a decision under section 61.
The permit applicant referred to Merunovich v Melbourne CC [2015] VCAT 609, in which the Tribunal stated:
A decision to grant a permit does not constitute the grant of a permit. The responsible authority must not issue the permit until the end of the period within which an objector may apply to the Tribunal for a review of the decision to grant the permit; or if an application for review is made within that period, until the application is determined by the Tribunal or withdrawn. Thus in the case of a notice of decision to grant a permit, there is no grant of a statutory authorisation until the permit is issued.
However, the Tribunal elected to not follow Merunovich, stating that it is possible that the Tribunal in that case meant to state that, “a decision to grant a permit under section 61 does not constitute the issue of a permit if objections have been received, in accordance with section 64”.
As well as the issue of statutory authorisation, the permit applicant argued that the proposal is not a high impact activity because it is not either constructing or carrying out works for three dwellings on a lot or allotment or using a lot or allotment for three dwellings; rather, the activity is constructing or carrying out works for one dwelling on one lot following subdivision of the subject land and using each one of the lots for one dwelling. However, the Tribunal dismissed this contention on a number of grounds, including the fact that the Council decision relevantly allows construction and use of ‘3 dwellings’ on the subject land.
See also:
- Guide to Planning Appeals: Cultural Heritage Management Plan > Exemption from requiring a CHMP
3. Whether a re-subdivision in the RCZ it will result in an increase of dwellings
Clause 35.06-3 of the Rural Conservation Zone (RCZ) states:
Each lot must be at least the area specified for the land in a schedule to this zone. If no area is specified, each lot must be at least 40 hectares.
A permit may be granted to create smaller lots if any of the following apply:
-
- The subdivision is the re-subdivision of existing lots, the number of lots is not increased, and the number of dwellings that the land could be used for does not increase.
- The subdivision is by a public authority or utility service provider to create a lot for a utility installation.
A permit must not be granted which would allow a separate lot to be created for land containing a small second dwelling.
In Murphy v Nillumbik SC [2023] VCAT 1337, Council refused an application for the re-subdivision of three lots in the RCZ. The property was also subject to the Bushfire Management Overlay.
The RCZ schedule in the Nillumbik Planning Scheme sets a minimum lot size of 8 hectares in the area subject to the proposal being considered by the Tribunal.
The Council contended that existing Lot B could not practically be used for a dwelling and therefore the subdivision will result in lots that could be used for three dwellings when currently the land can only support two dwellings, being the existing dwellings on Lots A and C.
The permit applicant referred the Tribunal to a number of cases where it was identified that there are two approaches to considering whether a subdivision will create additional dwellings: the ‘legal possibility’ approach and the ‘factual feasibility’ approach. The permit applicant then referred to previous Tribunal decisions that determined whether the number of dwellings that land could be used for was increased, including Rimic v Mornington Peninsula SC [2017] VCAT 239 and Green Wedge Protection Group Inc v Nillumbik SC [2006] VCAT 511.
The legal possibility approach also requires a degree of determining if there is a factual feasibility of a dwelling being established on each lot, which was considered in Selleck v Yarra Ranges SC [2018] VCAT 1786.
Having regard to the above cases, the Tribunal stated that that the test of Clause 35.06-3 is not whether a new dwelling would be approved on Lot B, while retaining the existing dwelling on Lot C, the test is whether a decision maker is satisfied that the number of dwellings that could be established across the three lots does not increase. Despite a number of constraints occurring on Lot B, the Tribunal was satisfied that, both legally and factually, that the number of dwellings the land could be used for does not increase with the proposed re-subdivision.
However, the Tribunal noted that this does not mean a permit must be granted for the re-subdivision, and that it is still necessary to determine if the proposed new subdivision alignment is acceptable having regard to the decision guidelines of the zone and Clause 65.02. It found the proposed subdivision proposal is an acceptable response to the RCZ objectives and rural landscape objectives for the area.
See also:
- Guide to Planning Appeals: Subdivision > Increase of dwellings
4. Non-complying car stackers
Use of car stackers to meet car parking requirements has generated some opposition from local residents over recent years, with some people not convinced they will be fully utilised given their relative inconvenience to access. Notwithstanding, many car stackers have been installed in apartment developments, and they are not only confined to the inner suburbs.
In two recent cases the Tribunal has supported responsible authorities in their quest to have car stackers comply with conditions of permit.
In the first case, Manningham CC v Alpine Developments Pty Ltd & Ors [2023] VCAT 1349, the Tribunal granted an enforcement order for breach of a permit that did not contain the approved car stacker.
The Council received complaints from residents and the owners corporation that the eight double car stackers were too small and cannot be used to park vehicles. On inspection the Council found that the dimensions of the car stackers are smaller than the dimensions shown on the 2016 endorsed plans. While a small car can squeeze into the stacker, the width of the car parks is insufficient to enable a person to get in or out of a vehicle due to inadequate clearance on either side.
The permit holder submitted an enforcement order cannot be made against it as the Council approved the works under the planning permit and as a result the planning permit is spent. However, the Tribunal found, as stated in Benedetti v Moonee Valley City Council [2005] VSC 434, a development permit does not expire following completion of the development. Further, in Box v Moreland CC (Including Summary) (Red Dot) [2014] VCAT 246 the Tribunal followed Benedetti and found that the condition did not cease to have effect simply because the land has been subdivided. A permit was required in Benedetti when the existing building was constructed. The permit applicant has in this case taken the benefit.
Whilst a demolition and building permit will need to be obtained given the owners of the car stackers and the owners corporation have not opposed the making of the order, the Tribunal did not expect there would be an issue in obtaining these permits.
In the second case, Chu v Whitehorse CC [2023] VCAT 1418, the Tribunal refused to amend a permit for the retrospective approval of the installed car stacker. The Council was opposed to the installed car stacker system because it considered the stackers can only accommodate small cars and will unreasonably restrict the usability and functionality of car parking in the development.
The Tribunal shared the Council’s concern that limiting 50 per cent of the car stacker spaces to small cars would unreasonably and unnecessarily constrain the usability and functionality of the car stackers. This is particularly the case for a development that is comprised of substantial multi-storey townhouses, with ten of the dwellings containing three or more bedrooms. Nor was the Tribunal satisfied that modification proposed via expert evidence on behalf of the permit holder would adequately solve the situation.
Retrofitting car stackers in the basement of apartment buildings may not be an easy task. However, the Tribunal has in the two cases above not tolerated car stackers that do not comply. Those people with a concern with car stackers (and the apartment occupiers too) will no doubt welcome these outcomes.
See also:
- Guide to Planning Appeals: Car parking > Car parking stackers
5. Minister’s decision to approve Surf Coast Statement of Planning Policy free from error
Practitioners will be aware that the state government has developed Statement of Planning Policies covering regional areas of distinctive landscapes, including Macedon Ranges, Bass Coast, Bellarine Peninsula and Surf Coast.
The introduction of the Surf Coast Statement of Planning Policy (SPP) has been delayed by a Supreme Court challenge in Zeally Investments Pty Ltd v Minister for Planning [2023] VSC 755 that the Minister’s decision to approve the SPP was invalid on a number of grounds, including:
- the Minister did not consult when preparing the Surf Coast SPP as required by section 46AW of the Planning and Environment Act 1987 (P&E Act);
- the Minister acted irrationally or unreasonably in making the Finalisation Decision, specifically in concluding that his preferred settlement boundary would not compromise land supply;
- the Minister’s consideration of land supply constraints was not in accordance with the P&E Act; and
- the Finalisation Decision was affected by bias in the form of prejudgment.
The appeal to the Supreme Court also challenged the decision of Surf Coast Shire Council to endorse the SPP.
The Plaintiffs own or have an interest in about half the land in the Spring Creek area of Torquay, specifically an area of 87 hectares at 80 Duffields Road, Torquay and an area of 38 hectares at 140 Duffields Road, Torquay.
The Supreme Court held that none of the Plaintiff’s grounds were made out and dismissed the appeal.
By way of background, the advisory committee that considered the SPP departed from two options included in the draft SPP for the Spring Creek area (see Distinctive Areas and Landscapes Standing Advisory Committee – Referral No 1 (AC) [2021] PPV 47 PPV Vol 9 No 5). Option 1 was to provide a low density ecological sustainable development with the current settlement boundary retained; Option 2 was to provide a ‘green break area’ whereby Spring Creek would form part of the surrounding green break between Torquay-Jan Juc and Bellbrae. However, the advisory committee recommended against the two options and instead recommended the area already in the Urban Growth Zone should be included in the protected settlement boundary and be permitted to develop, subject to a further limited review of the Council adopted Precinct Structure Plan and Native Vegetation Precinct Plan.
On the first ground, the Court held that:
- the consultation that took place before the second declaration took effect on 20 September 2021 was consultation undertaken ‘when preparing’ the Surf Coast SPP for the Surf Coast declared area;
- section 46AW of the P&E Act did not oblige the Minister to consult in relation to the third option for the Spring Creek area; and
- even if it had, the fact that the Minister did not seek views about the third option did not deny anyone — least of all the plaintiffs — a meaningful opportunity to make an intelligent response about the placement of the protected settlement boundary for Torquay-Jan Juc.
On the second ground, which related to land supply for housing, the Court held that it was apparent that the Minister did not express a conclusion that the Surf Coast municipality would realise its 15 year housing supply obligations without residential development of the Spring Creek area. Specifically, the Minister considered that the constraint in Spring Creek could be met by increased infill development, which could be sensitively managed by planning controls and policy, and by land supply in other parts of the municipality, including Winchelsea.
On the third ground, which also relates to the Minister’s consideration of land supply constraints, the Court held that the second part of the first sentence of the Reasons — ‘and in any event, land supply constraints would not be a reason to facilitate conventional subdivision in an area declared as a distinctive landscape’ – was a statement that must be read fairly and in the context of the Reasons as a whole, not narrowly or pedantically, and without an ‘over-zealous parsing’ of the Reasons.
On the final ground concerning the Minister’s decision, the Court held that a finding of actual bias was not open on the evidence. It stated:
The media statements attributed to the Premier or to other members of the Government are not probative of the Minister’s subjective state of mind. The only evidence of the Minister’s subjective statement of mind is the Reasons for the Finalisation Decision, and statements attributed to him in the media releases of 27 September 2018 and 30 October 2018. That evidence does not come close to establishing that the Minister approached the finalisation of the Surf Coast SPP with a mind that was closed and incapable of alteration by evidence and argument about the future development of the Spring Creek area. To the contrary, the evidence is that, while the Minister was predisposed against conventional residential development of Spring Creek, he was open to persuasion on that question.[162]
The Court also dismissed the grounds of appeal in relation to the Surf Coast Shire’s decision to endorse the SPP.
See also:
- Guide to Planning Appeals: Planning Schemes (Amendments to planning schemes) > Relief against Minister’s decision
6. Is permission required for stores and warehouses more than 30m from residentially zoned land?
In Hallmarc Developments Pty Ltd v Hobsons Bay CC (Corrected) [2023] VCAT 1365, the Tribunal considered a refusal for a use and development of 182 warehouses and stores on land in the Industrial 3 Zone. Council’s concerns related to integrated transport, urban design and drainage.
The Applicant proposed to build and manage the industrial estate, which the Tribunal was informed is an uncommon form of industrial development in Victoria, but is one that the Applicant has practiced for over 20 years.
At the Hearing, the Tribunal queried whether:
- permission was sought for the warehouses and stores that were more than 30m away from the residentially zoned land; and
- the warehouses and stores could be used for the other uses without requiring planning permission.
The Applicant submitted:
- The Tribunal must assess the application based on what is proposed, not on the speculative basis of what might occur in the future, or based on some hypothesised potential amendment that could be applied for. To do otherwise would be an error of law.
- The following extract from Able Demolitions & Excavations Pty Ltd v Yarra Ranges Shire Council [2008] VSC 294 at [22] makes this clear:
The proper characterisation of a planning permit application, which is constituted by the application form and any supporting plans, is a question of law. The applicant’s subjective intention is irrelevant; what is relevant is the applicant’s intention disclosed by the application.
- If a permit is granted for the proposal, the permit will require the site to be used as is proposed. There will be no scope under this permit for a different land use to occur, or for the approved land use to change to something else (at least without an amendment to the permit).
Further, it was submitted that while the permitted buildings and associated works are in place, the permit is not spent. As per Benedetti v Moonee Valley City Council [2005] VSC 434, an ongoing benefit is provided to use the land for warehouses along with ongoing burdens to maintain the buildings and works, including the access and drainage infrastructure and that no other uses are permitted without amending the proposed permit given contains a permit condition that the use and development as shown on the endorsed plans must not be altered without the prior written consent of the Responsible Authority.
On the other hand, the Council submitted that once the buildings are constructed, an ‘as of right’ uses can occupy any building that is 30m distant from the residentially zoned land without breaching the Planning Scheme or the planning permit. It submitted that the planning scheme turns on the finding in Able Demolitions that ‘the land’ is limited to the area proposed to be used for the stated purpose. In this case, it would be the land occupied by the building proposed to be used for the ‘as of right’ use rather than the entire site. As it would be 30m away from the residentially zoned land, the intent of the Zone is to allow it to be used ‘as of right’.
Because the buildings proposed to be used ‘as of right’ derive no benefit from the permitted warehouse use in the terms outlined in Benedetti, this aspect of the permit is spent.
Further, it rhetorically asked: what would constitute the assessment of an application for an ‘as of right’ use? It stated that there would be no need to alter the section of the permit titled ‘What the permit allows’ given that the proposed use is ‘as of right’. And further, it stated that the practical consequences of the alternative conclusion, being the Applicant’s position, is contrary to common practice in the Industrial 3 Zone.
In supporting the Applicant’s contentions, the Tribunal stated:
I find that the applicant’s submissions are correct. I regard the use aspect of the permit as creating ongoing restrictions on how the land can be used. I consider that Condition 2 of the permit confirms this. I accept that this restriction can be lifted but only through amending the permit and endorsed plans or, in appropriate circumstances, by the council giving its written consent.
I am not persuaded by the council’s submission on ‘the land’. It does not address the restrictions imposed by the permit. Each building on the endorsed plans is nominated for a particular use notwithstanding its distance from the residentially zoned land. I regard these nominations as ongoing restrictions.
I am not persuaded by the council’s submission that these restrictions are contrary to the intent of Planning Scheme regarding ‘as of right’ uses in the Industrial 3 Zone. As determined in Benedetti, a condition on a permit can impose a greater degree of land use regulation than does the Planning Scheme control itself. As to why the application proposes this greater degree of regulation, I accept as reasonable the applicant’s submission that:
The land uses that are proposed have been carefully chosen in part because they are benign, and because they generate low traffic rates. In this way, they respond to the context and constraints of the site. The fact that they do is no accident.
I am not persuaded by the council’s submissions on the planning permit. The restrictive benefit of the warehouse use cannot be ignored as it is embedded in the permit and endorsed plans. That it may be spent by the introduction of an ‘as of right’ use is not relevant given that allowing such a use requires either an amendment to the permit or the council’s written consent. [29-32]
See also:
- Guide to Planning Appeals: Warehouse, Permit > Whether spent
7. Be prepared: Local residents seek enforcement order to stop a scout’s performing arts centre
Many suburbs throughout metropolitan Melbourne are dotted with ageing scout halls. It could be argued that many of the halls are under-utilised, with use limited to evening scout sessions.
In Denning v Whitehorse CC [2023] VCAT 1414, a number of local residents sought an enforcement order and interim enforcement order (IEO) against the use of an existing scout hall for a performing arts centre in Blackburn South. It was alleged, inter alia, that there had been an increased use of the site, more noise, an extension of the hall building and the construction of other structures.
The property is owned by the Scout Association of Australia. The Association opposed the making of an IEO and submitted the subject land has been used as a scout hall for scouting activities for 60 years notwithstanding the level of activity undertaken from the subject land over the years may have varied.
Specifically, evidence was provided that since at least 1993, the subject land has been used for many uses including: performing arts; scouting activities; regular rehearsal venue for musical and theatrical performances; writing scripts; and constructing sets.
As to whether an IEO should be issued, the Tribunal identified two questions to be considered: Is there a serious question to be tried? And where does the balance of convenience lie? Reference was made to Metroll Victoria Pty Ltd v Wyndham CC [2007] VCAT 748, which considered the two above questions in some detail.
On the first question, the Tribunal held that, having regard to the evidence and submissions, it considered there is a serious question to be tried in this proceeding, namely whether the Respondent can lawfully undertake the alleged use and activities on the subject land.
On the second question, the Tribunal accepted the Scout’s evidence that it will not be able to prepare for its annual Melbourne Gang Show, including rehearsals and will be restricted from using the subject land for scouting activities for which it says it has existing use rights. Accordingly, the Tribunal found that the outcome that carries with it a lower risk of injustice if it turns out to be wrong is, to refuse to make the IEO. In reaching this conclusion, the Tribunal stated:
This is a difficult decision which I do not make easily nor lightly. The fact the subject land is within a residential area, and residents have brought this application is a serious matter. Given the community focus of the respondent, it should ensure that all noise, traffic and amenity impacts are kept to a minimum until this proceeding is finally resolved. [45]
The Tribunal refused the IEO but listed the proceeding for a compulsory conference.
See also:
- Guide to Planning Appeals: Enforcement Order (including interim enforcement orders)