1. Creamery Road PSP – draft planning scheme amendment to progress subject to further work
In Northern and Western Geelong Growth Areas Projects Standing Advisory Committee Referral 1 -Volume 1 Report (AC) [2025] PPV 22, the Minister for Planning appointed a standing advisory committee (the Committee) to:
… to provide timely advice to the Minister for Planning and the council on specific matters referred to it related to implementation of the Northern and Western Geelong Growth Areas Framework Plan such as precinct structure plans (PSP), development contributions plans, biodiversity conservation strategy and any associated draft planning scheme amendments.
The initiative to appoint an advisory committee to consider a draft amendment contrasts with the usual approach to appoint a Panel pursuant to section 153 of the Planning and Environment Act 1987 following exhibition of a planning scheme amendment and consideration of written submissions.
The Creamery Road Precinct considered by the Committee is located in the Western Geelong Growth Area (WGGA), is around 345 hectares and is the first precinct to be developed in the Northern and Western Geelong Growth Areas (NWGGA).
The PSP provides 195.717 hectares of NDA (56.80 percent) and anticipates approximately 3,645 dwellings and 10,200 residents.
Council submitted that the PSP includes innovative components not typically found in Victorian PSPs, including in particular the Clever and Creative Corridor (CCC) and smart city technology, as well as provisions that provides for and addresses social and affordable housing, environmentally sustainable design, net zero carbon requirements. and tree canopy cover targets.
Under its terms of reference, the Committee was asked to focus on two specific matters:
- The extent of developable land in the draft Creamery Road PSP, having regard to land required for active and passive open space, conservation reserves, schools and community facilities, transport infrastructure and drainage assets; and
- The development infrastructure levy, including the design, cost and apportionment of infrastructure items (in particular, the ‘Clever and Creative Corridor’ and drainage assets), as proposed in the draft Creamery Road DCP (a development infrastructure levy of approximately $1.6 million per net developable hectare is proposed).
In addition, the Committee was asked to:
…provide a report following the initial assessment which outlines any further work that needs to be undertaken or any changes required to be made to the draft Amendment prior to public exhibition to ensure a suitable development outcome.
The Committee adopted an innovative approach to its tasks, including a targeted process to assess the two specific matters it was asked to consider. It consulted with parties through:
- exchange of written submissions and evidence; and
- roundtable discussions.
The Committee’s directions provided parties and experts an opportunity to identify and resolve issues, to the extent possible, before the roundtable discussions started so the Committee could focus on unresolved issues during the roundtable.
In its executive summary, the Committee recorded is appreciation of the efforts and productive approach of parties and experts who participated in its consultation process.
The overarching issues were whether:
- there are viable options to increase the extent of developable land (Net Developable Area/NDA)
- there are viable options to reduce the development infrastructure levy (DIL)
- the draft Amendment will provide for a balanced development outcome.
Key unresolved issues related to whether:
- infrastructure items were appropriate and required to service the Precinct
- infrastructure should be ‘basic and essential’, and the type and standard of infrastructure items complied with the Development Contributions Guidelines (June 2003, amended March 2007) (DCP Guidelines)
- inclusion of shared infrastructure items was adequately justified
- State infrastructure should be included in the DCP
- the land valuation methodology is appropriate
- the Clever and Creative Corridor (CCC) should be included in the Precinct, and if so how it should be designed and funded
- the Evans Road Link, between the Western Geelong Growth Area (WGGA) and Northern Geelong Growth Area (NGGA), should be included in the DCP
- design parameters for Evans Road within the Precinct are appropriate
- the drainage strategy is appropriate
- the overall provision of open space is appropriate
- the provision of sports reserves, community facilities and non-government schools is appropriate
- the proposed location and density of housing is appropriate
- provisions relating to social and affordable housing are appropriate
- provisions relating to the Cowies Creek conservation area are appropriate.
Overall, the Committee found there are significant opportunities to improve efficiency of land use and maximise development opportunities to achieve a more balanced development outcome. There is potential to increase the extent of developable land and significant potential to reduce the development infrastructure levy, and the Committee made recommendations for further work to achieve this. In making recommendations for further work the Committee was mindful of the need for timely delivery of development.
The Committee was not able to be specific about the extent of increase in developable land and decrease in development infrastructure levy as this will need to be determined following the completion of further work. However, based on assessment of alternatives presented to it during the consultation process the greatest opportunities relate to transport, drainage, open space and community infrastructure.
The draft Amendment, including the PSP and DCP, will need to be finalised following completion of the recommended further work.
The Committee proposed 10 detailed recommendations to address the further work required.
Practitioners involved in PSPs will be well aware of the complexity of PSPs. A number of PSPs have suffered significant delays over the years because of the failure to resolve threshold issues during the preparation stage. In recognition of this experience, the Victoria Planning Authority has moved in some cases to undertake “due diligence” investigations prior to formally preparing a PSP. The more deliberative approach adopted by the Minister with the Creamery Road PSP may also be an effective method to address complex issues through an advisory committee process. It is not known at this stage whether the Creamery Road PSP planning scheme amendment will be formally exhibited and subject to the normal Panel processes, or whether it will be fast-tracked via a section 20(2) process.
See also:
- Guide to Planning Appeals: Precinct Structure Plans
2. Shepparton South East PSP and DCP – piloting new approaches to greenfield development
In Victorian Planning Authority Standing Advisory Committee Referral 9 Report (AC) [2024] PPV 44, which was released by the Minister in June 2025, it was proposed to implement the Shepparton South Precinct Structure Plan and DCP that proposed to provide for:
- more than 2,500 houses for more than 6,000 residents, and capacity for 275 jobs
- open spaces, recreational areas, community facilities and services and local retails spaces
- upgraded and new roads and transport infrastructure providing for local bus routes, and bicycle and pedestrian paths.
The VPA advised the Standing Committee (the Committee) that it was piloting new approaches to inform and reflect emerging government policy for greenfield development. This included new approaches to development staging, including “hard stage gates”, planning cost recovery and full cost recovery apportionment for State significant road infrastructure. The hard stage gate proposed includes a lot cap to ensure critical transport infrastructure is delivered in a timely fashion on Doyles Road, which is part of the Principal Freight Network. The proposed lot cap requires the intersections at Poplar Avenue/ Doyles Road and Channel Road/Doyles Road to be constructed prior to the issue of a permit for subdivision that results in a combined total of more than 800 residential lots.
It is also noteworthy that the VPA and the Greater Shepparton City Council were joint proponents for the Amendment. Whilst the Council had lodged a written submission following exhibition of the Amendment, it was withdrawn prior to the commencement of the Hearing process.
Overall, the Committee found that strategic justification for development of the precinct for residential growth is unequivocal. It considered there is strong support in various relevant strategic plans and the Planning Scheme and the need for more housing in Shepparton is well established. The proposal will deliver net community benefit and sustainable development, and delivery of the PSP will facilitate much needed, well located and well serviced residential development within Shepparton’s settlement boundary.
The Committee concluded the draft Greater Shepparton Planning Scheme Amendment C117gshe:
- is supported by, and implements, the relevant sections of the Planning Policy Framework
- is consistent with the relevant Ministerial Directions and Practice Notes
- is well founded and strategically justified
- should proceed subject to addressing the specific issues as discussed in this Report.
With respect to the lot cap, which is to ensure that the intersection works are constructed before the occupation of dwellings and to ensure that funding to achieve this is made available, the Committee considered that, whilst supporting the approach, there would be no harm in allowing some discretion for subdivision permits to be issued once certainty of the timing of the completion of the intersection upgrades are known. Accordingly, the Urban Growth Zone Schedule 2 should allow discretion for subdivision permits to be issued after the lot cap is reached.
Detailed findings were made by the Committee in relation to flooding and drainage, pedestrian signals, shared path along Broken River, community centre, sports reserve and school site and housing and density.
The Committee also found the DCP rate was acceptable, subject to amendments resulting from revised scope of specific infrastructure projects recommended by the Committee. It considered housing affordability will not be unduly affected by the DCP rate.
For practitioners of greenfield development long concerned with lack of basic infrastructure to service new urban growth areas, the VPA’s new approach is welcomed. Embedding a more integrated approach between planning and provision of infrastructure as part of the statutory process should bring more confidence that liveability in the greenfield can be achieved.
See also:
- Guide to Planning Appeals: Precinct Structure Plans
3. Greater Bendigo’s industrial future
In Greater Bendigo C282gben(PSA) [2025] PPV 33, the Panel considered an Amendment to partially implement the Greater Bendigo Industrial Land Development Strategy, June 2024 (GBILDS) and introduce the Greater Bendigo Industrial Development Guidelines, 2024 as a policy document in the Greater Bendigo Planning Scheme.
Specifically, the Amendment proposed a number of changes to local policy provisions in the Planning Scheme and to rezone two sites from industrial zones to other zones.
The GBILDS identified a significant expected shortage of industrial land supply, particularly of large and medium lots. In response Council undertook a detailed needs assessment and site selection process to identify a new industrial precinct within the municipality. This process identified a 294 hectare area south of the Marong township as a future investigation area to accommodate industrial growth. This investigation area is now known as the Bendigo Regional Employment Precinct (BREP).
The BREP area was adopted by Council as a preferred location to establish a new industrial precinct and as part of an active development facilitation role, Council purchased 155 hectares of land within the investigation area. At the request of Council, in February 2022, the Minister for Planning appointed the VPA as the planning authority for the rezoning and associated planning of the BREP.
In 2022, Council commissioned consultants to consider the impact of the Marong Business Park (MBP) and the BREP on the future industrial land supply. As a result, the GBILDS was amended to include the details of BREP and other minor changes to ensure the strategy reflected the state of industrial land supply for Greater Bendigo in 2024. The updated GBILDS was adopted Council in June 2024.
Some of the submissions questioned the accuracy of the forecast amount of industrial land for a 30 year supply pipeline outlined in the GBILDS and the need for the extent of industrial land identified for both the BREP and the MBP.
The Panel supported the partial implementation of the Amendment, stating that:
The Panel notes that the GBILDS contains precinct specific recommendations with an implementation time frame that ranges from months to 5 – 10 years. In the Panel’s view, Council’s approach of implementing the GBILDS through a number of amendments is appropriate given the magnitude of the task in front of it. The GBILDS is a sound strategic document based on a vision and eight principles that define objectives, precinct specific recommendations and actions with specific timelines.
One submitter challenged the GBILDS assessment that to meet demand Greater Bendigo will need an additional 170 to 270 hectares of industrial land in addition to the existing supply over the next 30 years. The submission noted that the 2024 land supply figure is substantially less than in earlier versions of GBILDS and questioned the analysis and data on which the 2024 update is based.
In response, Council submitted the 2020 version of GBILDS identified that in addition to the remaining 100 hectares of available industrial land, an additional 170 hectares of supply would be needed over the next 30 years.
Further, Council submitted the Review of Future Industrial Land Supply in Bendigo also identified a number of land supply constraints including land banking, proximity to existing residential development, vegetation cover and accessibility that would reduce supply and concluded between 170 and 270 hectares of land supply would be needed over the next 30 years.
Council acknowledged that the BREP and MBP could create more industrial land than is required to meet forecasted demand in the “short to medium term.” However, it submitted that a long term pipeline of industrial land is justified because Greater Bendigo faces significant challenges in the provision of large sites and by the time the land is development ready it is likely 20 years will have elapsed.
The Panel was satisfied that the 170 to 270 hectares is based on the work undertaken and the detailed analysis in two independent reports. It stated:
The Panel also accepts Council’s submission that the MRP and BREP will not be development ready for some time and that providing for a pipeline of available industrial land is a sound long term strategy.
The Panel recommended that the Amendment be adopted subject to changes.
See also:
- Guide to Planning Panels: Industrial strategies and design guidelines
4. Support for Beveridge North West PSP and quarry permit
Almost three years after the Beveridge North West PSP advisory committee completed its report, the Minister for Planning has released the report and approved a planning scheme amendment and a planning permit for a quarry (see Beveridge North West Precinct Structure Plan, Supplementary Levy Infrastructure Contributions Plan and Quarry Permit Application Advisory Committee (AC) [2022] PPV 64).
The Beveridge North West Precinct Structure Plan (PSP), Supplementary Levy Infrastructure Contributions Plan (ICP) and Quarry Planning Permit Application Ministerial Advisory Committee was appointed by the Minister for Planning in early 2022 with three major tasks:
- to advise the Minister whether draft amendment C158mith is acceptable and implements the recommendations of the Amendment C106 Panel
- to advise the Minister whether draft Amendment C161mith is acceptable
- to advise the Minister whether a planning permit should issue for a quarry in the north east corner of the PSP area on Work Authority Application Area 1473, and if so with what conditions.
Amendment C106 previously sought to introduce the PSP into the Mitchell Planning Scheme by changes to zones and overlays and the inclusion of the PSP as an Incorporated Document.
The Panel made 17 recommendations in relation to the Rural Conservation Zone (RCZ), affordable housing, bushfire, and biodiversity. Notably, the Panel recommended that the PSP be revised to include the opportunity for resource extraction.
A planning permit application for a stone quarry in the north east corner of the PSP had been lodged with the Council, however the application was not before the Panel although it was the subject of discussion throughout the Hearing.
The Panel concluded that there was clear policy support for the extraction of the stone resource in planning policy and recommended that Amendment C106 be revised to explicitly include precinct level planning for resource extraction.
Amendment C158 proposes to introduce the PSP into the Planning Scheme while introducing a specific control to allow a time limited quarry on the quarry land. Significant changes to the PSP from Amendment C106 include planning for the quarry and the recognition of the burrung buluk wetland. Amendment C158 proposes to introduce an ICP to enable the collection of funds for infrastructure through development. The ICP includes a supplementary levy to account for development on dispersive sodic soils.
The quarry permit application was called in from VCAT by the Minister for Planning, and if a permit is to issue, it will be issued by the Governor in Council.
Key issues raised in submissions on the quarry and PSP included:
- amenity including noise and dust
- safety including blasting
- traffic concerns for movement of quarry materials on to the Northern Highway
- strategic planning, primarily that a quarry is not suitable in an area with an identified urban future
- how the quarry can be integrated into the PSP and whether buffers can be reduced over time
- the impact of buffers on surrounding land
- quarry end of life and rehabilitation
- PSP development issues around roads and community infrastructure from specific landowners
- the treatment of the burrung buluk wetland in the PSP
- the need for extractive industries in development and employment (noted in supporting submissions on the quarry).
The Committee noted that the planning permit application for the quarry is clearly an issue of significant concern to the local community and Council. Based on the evidence before it however, the Committee considered that a quarry, limited through the planning controls for 30 years (until 2052), will not result in unacceptable impacts and a permit should be issued.
One of the key issues addressed by the Committee was whether a planning permit can issue for the quarry given that the Applicant is relying on an amended version of the Work Plan which has not been statutorily endorsed, having regard to Sandow v Macedon Ranges SC [2017] VCAT 501. The Committee stated:
The assessment process for considering extractive industry proposals under the MRSD Act and the PE Act is articulated in PPN89. It is clear that the process has been developed to ensure that both Acts ‘speak to each other’ to ensure consistency in planning and decision making for quarries from the technical and land use planning perspectives.
When the SEWP was endorsed in 2015, the Committee understands that it was to support a quarry planning permit application entirely consistent with the SEWP. Since that time there have been many changes in the planning context, including the development of the PSP and the Amendment C106 Panel report, and its acceptance by the Minister.
The Committee considers this context is important. The changes to the original quarry proposal have been driven by the need to better integrate it in a land use context that has a clear urban development future. The changes are all aimed at reducing its risks and impacts when compared to the proposal in the SEWP. In the Hearing there was considerable discussion beyond even the material in the permit application about, for example different quarrying schemes, plant location and buffer needs.
In these ‘extraordinary’ circumstances, the Committee considers it reasonable and appropriate to allow the proposal to develop from that included in the SEWP and even in the draft Work Plan. These could be said to be material changes (from the SEWP to the draft Work Plan), however they are material changes to reduce impact. From a policy point of view the Committee does not think it logical that the planning system would seek to prevent such an outcome.
Another key issue was in relation to the proposed two buffers to the quarry to reduce land use conflicts, an inner buffer (250 metres) and outer buffer (500 metres). The Committee found:
The starting point for consideration of the extent of buffers is set in EPA Publication 1518, and these distances have been included in the exhibited controls, as part of the SCO that is proposed to apply to the quarry and surrounding buffer land.
The Committee agree that the ‘activity’ boundary or extraction limit is the appropriate measurement point for the extent of likely impacts, and accepts the evidence that it is the activity boundary rather than title boundary that should inform the buffers. However for the purposes of the SCO in forming the quarry and its statutory buffer, the Committee agrees with the VPA that this overlay should be measured from 20 metres within the work authority boundary, as set out at clause 52.09-6 of the Planning Scheme. This will allow for not only the proposed quarry with its associated operational details, but also for an alternative extractive industry proposal in the event that the current application did not proceed. It will set the statutory framework in which detailed permit(s) and endorsed plans will be issued. The concept of retractable buffers is discussed in Chapter 6.3 below, and the Committee conclude that the activity boundary should be used in undertaking assessment of impacts at a particular phase of the quarry operations.
A related issue was whether to support a phasing plan of the quarrying activities, which would allow for a moving buffer; that is, a buffer taken from the extraction point of each stage, as the stages are developed over time. The Committee stated:
The framework for extractive industry as outlined in both the Planning Scheme and the MRSD Act requires impacts from extraction to be ‘eliminated or minimised as far as reasonably practicable’. While there are many ways in which this can theoretically be achieved, the retraction of buffers is one way to respond to this direction.
The Committee also notes that the EPA Publication 1518 state that buffers should commence from the ‘activity area’ rather than the quarry titles, and states as follows:
Measuring from the activity area allows for any separation that is provided within the property boundary of the industry site to be considered. If an industry changes its use or moves a relevant activity within the property boundary, the requirement for a planning permit and/or works approval should trigger reassessment of adequate separation distances. [Committee emphasis].
This appears to support the idea of buffers moving as the activity changes within the property boundary.
Finally, it is also relevant that the quarry Applicant is supportive of this approach.
On this basis, the Committee agrees that the buffers should retract over time to progressively unburden adjoining properties and allow for urban development of surrounding land as soon as is possible. The Committee notes that this support for retractable buffers is not for the extent of the SCO to change with each phase of quarrying, as this would require a planning scheme amendment to amend the boundaries of the overlay that would be unduly cumbersome (noting that could occur, however is not in the Committee’s view necessary for each phase). Rather, that the actual areas to be protected from quarry emissions move with each stage.
Just as significant an issue was whether the buffers should be controlled or owned by the quarry operator. The Committee stated:
Clause 14.03-1S of the Planning Scheme clearly directs that buffers are to be owned or controlled by the Applicant of extractive industry. However, it is acknowledged that in practice, this is rarely the case. This is largely because quarries were either established prior to this provision coming into place or have been located in areas remote from sensitive uses (other than say a rural dwelling), and using neighbouring rural land as a buffer to the quarry operations has had minimal impact on the economic use of the buffer land.
….
Overall, the Committee finds that some impost on neighbouring land, particularly in the shorter term while the land is used for rural purposes, is reasonable. However, at the stage where urban development contemplated by the PSP is curtailed on the buffer land by the quarry, that is, by the time the development front approaches the buffer land, ideally this loss should be compensated for by the quarry Applicant.
The retractable buffers will go some way to minimise the impacts, however, it is likely on the information provided to the Committee that the quarry operations will still prevent parts of the PSP proceeding for some years. The impost would remain on part of the YVW land across the entire time period, and for three of the four phases for Ms Gilbo’s land. It is partly for this reason (as well as other reasons discussed in Chapter 6.6) that the Committee supports the time limit of an overall time frame of 30 years, including rehabilitation, put forward by the VPA rather than the longer timeframe proposed by Conundrum.
The Committee notes that balancing the fair and economic interests of the landowners of the buffer and the broader net community benefits of stone extraction is difficult, and therefore has sought to strike an appropriate balance.
The Minister for Planning approved the Special Controls Overlay subject to:
- Allowing approximately 2,400 new lots in an area of approximately 140 hectares
- Prohibiting the development of further stages of the PSP until the Camerons Lane Interchange is operational or an earlier time as determined by the Minister for Planning.
The issue of the timing of the government road infrastructure was outside the Committee’s terms of reference, so was not addressed in the Committee’s report. No doubt the state government is feeling the pressure from northern growth area residents about the poor transport infrastructure in the corridor, particularly the time it takes to reach the Hume Freeway in peak periods. It can be argued this condition in the SCO will put pressure on the government to deliver the interchange sooner rather than later – that is, if the Minister does not invoke the ‘get out’ clause to approve more lots before the interchange is constructed.
As mentioned above, the Committee’s terms of reference did not include consideration of the timing of delivery of state infrastructure, which can be contrasted with the Shepparton South East PSP and DCP where a key issue addressed by that Committee was the integration of lot release and provision of infrastructure. It is noted the Beveridge North West PSP preceded the Shepparton South East PSP by two years.
See also:
- Guide to Planning Panels: Precinct Structure Plans