PPV Volume 11 No 3

1. Beaufort Bypass EES gets green light

As part of the Western Highway upgrade, the next section to be considered under a combined Environmental Effects Statement (ESS) and planning scheme amendment is the Beaufort Bypass, which is an 11 kilometre long, freeway standard dual carriageway that will bypass Beaufort and connect two recently duplicated sections of the Western Highway to the east and west of the Beaufort township.

Practitioners maybe aware of the part of the Western Highway upgrade between Buangor to Ararat has been subject to a number of legal challenges because of concerns about cultural heritage impacts.

In Beaufort Bypass Inquiry and Advisory Committee Report No 1 (EES) [2022] PPV 63, the Inquiry and Advisory Committee (IAC) found that:

The IAC considers the Project will bring positive benefits to Beaufort and surrounds and to regional Victoria. The Project will result in a net benefit for the community of Beaufort and Victoria more generally.

The impact of the Project’s construction on biodiversity and habitat, landscape and amenity will be significant for the wider community but particularly significant for adjacent landowners and those whose properties will be fully or partly acquired. While some of these impacts will remain for some time after the Project becomes operational, on balance, these impacts can be managed to an acceptable level through the implementation of the mitigation measures.

Perhaps of most concern identified by the IAC was the reliance on the reference design to assess impacts. It may be recalled this was a major concern for the IAC that considered the North East link (North East Link Project (EES) [2019] PPV 57).

In the current matter, the IAC stated:

The reference design approach used for this Project, while appropriate and sufficiently detailed to establish whether key impacts were acceptable, has its disbenefits. These included establishing how many of the critical Management Documents and mitigation measures, particularly those relating to biodiversity and habitat, landscaping and cultural heritage, would be integrated into the detailed design phase rather than be developed later in response to the final designs. It was also unclear as to whether critical design components such as the Camp Hill land bridge would be embedded into the design or remain optional depending on project funding.

The IAC has recommended an approach to provide overarching guidance for the detailed design process.

Your editors note that whilst acknowledging that detailed design of such major projects are difficult to produce pre-tender, it presents somewhat of a challenge to identify all major impacts, especially environmental impacts, during the environmental assessment stage.

See also:

  • Guide to Planning Panels Environmental Effects Statements > Major Roads

2. Revisions to Yarra Ranges’ Erosion Management Overlay

The purpose of the Erosion Management Overlay is:

To protect areas prone to erosion, landslip, other land degradation or coastal processes by minimising land disturbance and inappropriate development.

In Yarra Ranges PSA C217yran [2023] PPV 63, it was proposed to amend the current EMO to:

  • align it with the guidance provided in the Australian Geomechanics Society Practice Note Guidelines for Landslide Risk Management 2007
  • simplify the structure
  • introduce new permit exemptions.

Council received grant funding of $300,000 under the Commonwealth Government’s Preparing Australian Communities Program – Local, to undertake a review of the EMO. It followed a significant storm event in Victoria in June 2021, which resulted in the damage and destruction of dwellings in Yarra Ranges. Many of the affected properties were in the Dandenong Ranges and nearby areas, which are also susceptible to other natural hazards including bushfire and landslip.

Council submitted:

  • the current EMO requires all development to achieve a low or very low risk to property whether it be a garden shed or a hospital
  • the Amendment increases the tolerable risk for certain types of development, like residential dwellings or farm sheds
  • the tolerable risk for critical infrastructure such as a school or hospital will not change
  • the proposed risk profile is consistent with AGS 2007 Landslide Guidelines and with other planning schemes, including Colac Otway
  • the new approach will benefit the community who are facing difficulties rebuilding their homes after recent major storm events.

Engineering evidence provided for Council was that the applicable regulatory authority (i.e., Yarra Ranges Council) is ultimately responsible for deciding what risk level is tolerable.

Although there are guidelines to help inform the selection of a risk threshold, it is the responsible authority who must make this determination in line with societal expectations. For this Amendment, it was recommended that Council adopt the guidance set out in the AGS 2007 guidelines noting there is precedent from other Victorian LGA’s (Local Government Authorities) that have adopted this guidance.

In response to questions from the Panel, Council’s expert confirmed:

  • there is no standard for appropriate development in areas subject to erosion or landslip in Victoria
  • local governments rarely have in-house specialists with technical expertise in erosion and landslip
  • councils rely on technical advice from insured practitioners to inform permit decisions
  • AGS 2007 Landslide Guidelines are generally applied as a standard across Australia.

The Panel noted:

  • Council’s proposed benchmark for appropriate development (that is tolerate risk) is informed by an industry standard that is recommended by experts
  • this benchmark is referenced in the Colac Otway Planning Scheme.

It stated:

Unlike other risk based overlays in the Victoria Planning Provisions, development decisions under the EMO do not benefit from the input of an expert central agency, as is the case for bushfire (relevant fire authority), inundation and flooding (relevant floodplain management authority) and salinity (Secretary to the Department of Energy, Environment and Climate Action). The Panel notes the opinion of Mr Paul that local governments rarely have in-house engineering geologists, and decisions are informed by expert information accompanying an application. In this context, it is reasonable for Council to seek to set a benchmark for appropriate development, and to match that benchmark with an industry accepted standard that applies elsewhere in Victoria and Australia. The Panel is satisfied this approach is consistent with the strategic objective of the Planning Scheme to prevent inappropriate development. 

The importance of careful drafting of amendments is discussed in A Practitioner’s Guide to Victorian Planning Schemes Version 1.5, April 2022 (Practitioner’s Guide). This states: 

The efficiency and effectiveness of planning schemes is important to Victoria’s economy and liveability. Each year the planning system processes around 55,000 planning permit applications, which represents around $30 billion of future investment in Victoria.

Drafting is effective when it is clear and can be consistently understood by applicants and administered by decision makers. The Panel is not satisfied the exhibited Amendment will achieve its intended objective for administrative efficiency because drafting does not comply with Ministerial Direction 1: The Form and Content of Planning Schemes (Form and Content Direction) and the Practitioner’s Guide. This is discussed in detail in Chapters 3 and 4. Notwithstanding, the Panel is satisfied drafting issues can be remedied by the planning authority through future stages of the Amendment process.

Subject to its recommended changes, the Panel is satisfied the Amendment delivers net community benefit and sustainable development as required by Clause 71.02-3.

The Panel concluded that the Amendment:

  • is supported by, and implements, the relevant sections of the Planning Policy Framework
  • is well founded and strategically justified
  • should proceed subject to addressing the more specific issues raised in submissions.

See also: 

  • Guide to Planning Panels: Environmental policies > Erosion

3. Abandonment of rezoning of Bannockburn PPRZ land

A Council-initiated planning scheme amendment to rezone land in the Public Park and Recreation Zone to the Neighbourhood Residential Zone in Bannockburn has not gained support by an advisory committee in Priority Projects Standing Advisory Committee Referral 33 (AC) [2023] PPV 57.

The rezoning also included a combined application for planning permit to facilitate a 51 lot residential subdivision. The land is approximately 3.5 hectares and forms part of the 13.2 hectare Bannockburn Recreation Reserve. Council had declared the 13.2 hecatre site surplus to its needs.

The Minister’s terms of reference requested the Committee to constrain its specific advice to the following matters:

  • loss of public open space
  • amenity impacts from potential future medium density housing and social and affordable housing
  • lack of consultation on the decision to declare the land as surplus.

Many of the submissions received objected to Council’s decision to declare the land surplus. However, the advisory committee made clear that, whilst appreciating the proposed rezoning and future sale of the subject land are matters that are inextricably linked and that the rezoning advances the possibility of sale, it was not the role of Committee to review any intention of Council to dispose of the subject land.

In holding the rezoning lacked strategic justification, the advisory committee stated:

The Committee acknowledges that Council, like other landowners, have changing priorities over time that can include the need or desire to sell land. Council considers the loss of public open space in Dardel Drive justified as a proactive step to provide funding for alternative open space in their growth areas.

While the Committee understands these changing priorities, it agrees with Mr Trowell and Ms Jeavons that the appropriate strategic justification for the proposed rezoning and subdivision, has not been demonstrated. There has been no analysis of the nature and distribution of existing open space in Bannockburn or the municipality more broadly, to determine how this currently services the needs of residents and how it is projected to in the future. While Council submitted their open space and recreation planners have internally assessed this, no documentation was provided when requested by the Committee.

See also: 

  • Guide to Planning Panels: Public open space

4. Greater Geelong Advertising sign guidelines

In Greater Geelong C383ggee (PSA) [2023] PPV 66, which proposed the introduction of new advertising sign guidelines via an Incorporated Document, the Panel, whilst supporting the Amendment, recommended changes to ensure the guidelines are truly guidelines to assist discretionary decision-making, and are not seen as planning controls.

Some submitters concerned with the Amendment stated::

 ..guidelines should do no more than guide with general principles regarding positive outcome, and provide recommendations for techniques which may demonstrate one way in which amenity impacts might be reduced. Guidelines in planning policy that adopt a ‘one size fits all’ approach will inevitably fail to perform their proper role which is to guide a decision maker in its task of assessment of a permit application to determine whether the application will deliver an acceptable outcome.

The Panel considered that to resolve the drafting of proposed local policies at Clauses 15.01-1L and 15.01-6L, the intent of the 2022 Guidelines (as an Incorporated Document) must be properly understood. It therefore considered it is appropriate and practical for the meaning of ‘objectives’, ‘strategies’ and ‘guidelines’ in the 2022 Guidelines to align with Clause 71.02-2 (Operation) and the Practitioner’s Guide. This can be achieved by inserting new text into the ‘User Guide’ and relabelling ‘guidelines’ as ‘policy guidelines’, as proposed by Council.

In recommending the above approach, the Panel stated:

Policy guidelines provide detailed guidance on how a strategy is to be implemented or objective achieved by providing direct and prescriptive measures. However, a policy guideline only represents one way of achieving a desired outcome. Importantly, a responsible authority is not required to give effect to a policy guideline if it is satisfied an alternative approach can still fulfil the policy objectives and strategies. With this clarity, many of concerns expressed by submitters and experts fall away. Notably, the policy guidelines are:

    • not mandatory requirements
    • not elevated above strategies or objectives
    • deliberately directive about how a strategy can be implemented or an objective achieved
    • not the only method of implementing a strategy or meeting an objective.

Turning to Clauses 15.01-1L and 15.01-6L, the Panel finds the drafting agreed by Council and ACDC is unnecessarily confusing, because it provides a ‘strategy’ to “meet objectives, strategies and guidelines”. To avoid this confusion, and reinforce the equivalency between objectives, strategies and policy guidelines in the Planning Scheme and the 2022 Guidelines, the Panel’s preferred drafting is: 

Objective

To encourage signs to meet the objectives of the City of Greater Geelong Advertising Sign Guidelines (May 2022).

Strategy

Encourage signs to meet the strategies of the City of Greater Geelong Advertising Sign Guidelines (May 2022).

Policy Guidelines

Consider as relevant

Policy guidelines of the City of Greater Geelong Advertising Sign Guidelines (May 2022).

The remainder of the Panel report addresses the justification and wording of the various provisions proposed in the Guidelines.

See also:

  • Guide to Planning Panels: Local policies > Advertising signs

5. Victorian Murray Floodplain Restoration Project – Burra Creek Project recommended for abandonment

The Victorian Murray Floodplain Restoration Project (VMFRP) is being delivered as part of the Murray-Darling Basin Plan. The Basin Plan aims to increase water available for the environment and improve the health of the Murray River and its floodplains.

We have reported on two earlier reports, the Murray Floodplain Restoration Project EES Central (EES) [2023] PPV 17 (editorial comment Vol 11 No 1) and the VMFRP SIAC Report No. 2 – ER Central [2023] PPV. (editorial comment Vol 11 No 2). Both projects were recommended for approval subject to conditions.

In VMFRP SIAC Report No. 3 – ER Central (Burra Creek) [2023] PPV, the Standing Inquiry and Advisory Committee (SIAC) considered the Burra Creek Project. Its report is to be read together with SIAC Report No. 2 for the Nyah and Vinifera Projects, as many of the issues are common between all three ER Central projects.

Burra Creek is a branch of the Murray River extending over 50 kilometres through the Burra Creek floodplain. Prior to regulation of flows in the Murray River, the Burra Creek floodplain would have received inundation in most years, with high flows maintaining prolonged inundation in Burra Creek and associated billabongs and low-lying wetlands.

Below is the SIAC’s overall assessment:

It was not demonstrated to the Committee’s satisfaction that the Burra Creek Project will provide an overall benefit to the biodiversity values of the Burra Creek floodplain.

With the Wakool effect taken into account, the known hydrological requirements of existing vegetation communities on the floodplain are largely met by existing conditions, raising key questions about the need for the Project. Further, some existing vegetation communities on the floodplain will receive more inundation than recommended as a result of the updated Project Description. 

Two hydraulic models are discussed in the Addendum Report – the Jacobs Burra model and the Reconnecting River Country model (RRC model). The ER and Addendum Report rely on the Jacobs Burra model. 

Hydraulics on the Burra Creek floodplain are substantially and materially different to those predicted by the Jacobs Burra model, primarily because the Jacobs Burra model does not account for the Wakool effect. Despite understanding that the Wakool effect results in inundation of the floodplain from the north (not just the south as predicted by the Jacobs Burra model), the potential effects of Project infrastructure (including containment banks) on inundation processes at the northern end of the floodplain have not been assessed.

The RRC model does account for the Wakool effect, but is not suitable in its current form to model the hydraulic conditions on the Burra Creek floodplain. Limited outputs from the RRC model were used to inform the updated surface water assessment in the Addendum Report, but the updates to the remaining Specialist Assessments continued to rely on outputs from the Jacobs Burra model. Those outputs are likely to be inaccurate for key hydraulic parameters (including depths, velocity and bed shear stress). Limited reliance can therefore be placed on these Specialist Assessments.

Aside from the doubt about the need for the Project, and the uncertainties arising from the Jacobs Burra model, the assessments undertaken to date predict that the Project will result in:

    • a larger loss of native vegetation through both construction and operation compared to the Nyah or Vinifera Projects, including:
      • up to 188 Large Trees (including 76 Very Large Trees and 136 Hollow-bearing Trees) from construction and potential death of a further up to 132 Large Trees resulting from operation
      • permanent removal of up to 7.778 hectares of an endangered Ecological Vegetation Class (EVC) (EVC 103 Riverine Chenopod Woodland) through construction, with potential further loss of a small area (0.24 hectares) of Riverine Chenopod Woodland through Project operation
      • the transition of 50 hectares of Lignum Swampy Woodland on the floodplain to Lignum Swamp
    • mixed outcomes for threatened flora species present or possibly occurring in the project area, as Project operation is expected to:
      • benefit 18 aquatic, floodplain and mudflat, and moisture-dependent Flora and Fauna Guarantee Act 1988 (FFG Act) listed threatened flora species
      • have an adverse effect on 19 dryland FFG Act listed threatened flora species 

For these reasons, the Committee’s primary recommendation is that the Burra Creek Project not be approved. 

The SAIC made recommendations on changes to the Incorporated Document and the Environmental Delivery Standards and monitoring requirements should the Minister approve the project. These are largely based on the recommendations of the Nyah and Vinifera Committee, and have been modified to:

  • include additional requirements that are specific to the Burra Creek context
  • reflect the Minister’s Assessment for the EES Central Projects.

On 18 January 2024, the Minister announced that she supported the SIAC’s findings that the Burra Creek project will not deliver overall benefits for floodplain vegetation communities and associated biodiversity values, and further will have unacceptable environmental effects.

See also:

  • Guide to Planning Panels: Environmental Effects Statements > Floodplain management